An early cost estimation model for hydroelectric power plant projects using neural networks and multiple regression analysis

被引:19
作者
Gunduz, Murat [1 ]
Sahin, Haci Bayram [2 ]
机构
[1] Qatar Univ, Dept Civil Engn, Doha, Qatar
[2] Gestas Construct Ltd Co, Ankara, Turkey
关键词
early cost estimation; multiple regression analysis; artificial neural network; hydroelectric power plants;
D O I
10.3846/13923730.2014.890657
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Energy is increasingly becoming more important in today's world, whereas energy sources are drastically decreasing. One of the most valuable energy sources is hydro energy. Because of limited energy sources and excessive energy usage, cost of energy is rising. Among the electricity generation units, hydroelectric power plants are very important, since they are renewable energy sources and they have no fuel cost. To decide whether a hydroelectric power plant investment is feasible or not, project cost and amount of electricity generation of the investment should be precisely estimated. In this paper, fifty four hydroelectric power plant projects are analysed by using multiple regression and artificial neural network tools. As a result, two cost estimation models have been developed to estimate the hydroelectric power plant project cost in early stages of the project.
引用
收藏
页码:470 / 477
页数:8
相关论文
共 27 条
[11]   Case Adaptation Method of Case-Based Reasoning for Construction Cost Estimation in Korea [J].
Ji, Sae-Hyun ;
Park, Moonseo ;
Lee, Hyun-Soo .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2012, 138 (01) :43-52
[12]   CONSTRUCTION PROJECT CASH FLOW PLANNING USING THE PARETO OPTIMALITY EFFICIENCY NETWORK MODEL [J].
Jiang, Aiyin ;
Issa, Raja R. A. ;
Malek, Maged .
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2011, 17 (04) :510-519
[13]   Comparison of construction cost estimating models based on regression analysis, neural networks, and case-based reasoning [J].
Kim, GH ;
An, SH ;
Kang, KI .
BUILDING AND ENVIRONMENT, 2004, 39 (10) :1235-1242
[14]   A hybrid conceptual cost estimating model for large building projects [J].
Kim, Hyung-Jin ;
Seo, Yong-Chil ;
Hyun, Chang-Taek .
AUTOMATION IN CONSTRUCTION, 2012, 25 :72-81
[15]   Preliminary Cost Estimation Model Using Case-Based Reasoning and Genetic Algorithms [J].
Kim, Kyong Ju ;
Kim, Kyoungmin .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2010, 24 (06) :499-505
[16]   Approximate cost estimating model for river facility construction based on case-based reasoning with genetic algorithms [J].
Kim, Miseon ;
Lee, Siwook ;
Woo, Sungkwon ;
Shin, Do Hyoung .
KSCE JOURNAL OF CIVIL ENGINEERING, 2012, 16 (03) :283-292
[17]   DEVELOPING A CONSTRUCTION-DURATION MODEL BASED ON A HISTORICAL DATASET FOR BUILDING PROJECT [J].
Lin, Ming-Chiao ;
Tserng, Hui Ping ;
Ho, Shih-Ping ;
Young, Der-Liang .
JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2011, 17 (04) :529-539
[18]   Construction cost analysis under uncertainty with correlated cost risk analysis model [J].
Oekmen, Oeder ;
Oeztas, Ahmet .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2010, 28 (02) :203-212
[19]   Cost determination of the electro-mechanical equipment of a small hydro-power plant [J].
Ogayar, B. ;
Vidal, P. G. .
RENEWABLE ENERGY, 2009, 34 (01) :6-13
[20]   Early Cost Estimating of Road Tunnel Construction Using Neural Networks [J].
Petroutsatou, K. ;
Georgopoulos, E. ;
Lambropoulos, S. ;
Pantouvakis, J. P. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2012, 138 (06) :679-687