Understanding barriers to BIM implementation: Their impact across organizational levels in relation to BIM maturity

被引:55
作者
Siebelink, Sander [1 ]
Voordijk, Hans [1 ]
Endedijk, Maaike [2 ]
Adriaanse, Arjen [1 ]
机构
[1] Univ Twente, Fac Engn Technol, Dept Civil Engn, Enschede, Netherlands
[2] Univ Twente, Fac Behav Management & Social Sci, Dept Educ Sci, Enschede, Netherlands
关键词
building information modeling; implementation barriers; maturity; organizational levels; MANAGEMENT; CONSTRUCTION; CULTURE;
D O I
10.1007/s42524-019-0088-2
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This multiple case study of a contracting firm contributes to understanding the barriers that organizations face during the implementation of building information modeling (BIM) by providing insights into the impact of these barriers across different organizational levels (i.e., from top management to project teams) and by relating these barriers to different degrees of BIM maturity. First, we observe the dominance of barriers related to the motivation, competence, and time capacity of people across all levels of an organization. Second, the cluster of barriers at the middle-management level highlights the important role of this level in reducing these barriers. Third, only those cases with a low level of BIM maturity have struggled with lack of top management support, thereby highlighting the importance of such support in achieving BIM maturity growth. High BIM maturity situations are more prone to externally oriented barriers in attempting to further leverage the benefits of BIM. Our study provides insights on where to focus BIM implementation measures and how to enhance organizational BIM maturity.
引用
收藏
页码:236 / 257
页数:22
相关论文
共 45 条
[21]   Systematic process analysis: when and how to use it [J].
Hall, Peter A. .
EUROPEAN MANAGEMENT REVIEW, 2006, 3 (01) :24-31
[22]  
Holt DT, 2009, IND INNOV SER
[23]  
ISO/IEC, 2015, 330012015 ISOIEC
[24]   The impact of organizational culture and reshaping capabilities on change implementation success: The mediating role of readiness for change [J].
Jones, RA ;
Jimmieson, NL ;
Griffiths, A .
JOURNAL OF MANAGEMENT STUDIES, 2005, 42 (02) :361-386
[25]  
Kamara J.M., 2002, CONSTR INNOV-ENGL, P53
[26]   Rethinking project management and exploring virtual design and construction as a potential solution [J].
Li, Heng ;
Lu, Weisheng ;
Huang, Ting .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2009, 27 (04) :363-371
[27]  
Liu S., 2015, International Journal of Marketing Studies, V7, P162, DOI [10.5539/ijms.v7n6p162, DOI 10.5539/IJMS.V7N6P162]
[28]   The development of a supply chain management process maturity model using the concepts of business process orientation [J].
Lockamy, A ;
McCormack, K .
SUPPLY CHAIN MANAGEMENT-AN INTERNATIONAL JOURNAL, 2004, 9 (3-4) :272-278
[29]   Cost-benefit analysis of Building Information Modeling implementation in building projects through demystification of time-effort distribution curves [J].
Lu, Weisheng ;
Fung, Ada ;
Peng, Yi ;
Liang, Cong ;
Rowlinson, Steve .
BUILDING AND ENVIRONMENT, 2014, 82 :317-327
[30]  
Messner J., 2013, BIM planning guide for facility owners