Studying the impact of sequence-dependent set-up times in integrated process planning and scheduling with E-ACO heuristic

被引:18
作者
Zhang, Sicheng [1 ]
Wong, T. N. [1 ]
机构
[1] Univ Hong Kong, Dept Ind & Mfg Syst Engn, Hong Kong, Hong Kong, Peoples R China
关键词
integrated process planning and scheduling; job-shop scheduling; ant colony optimisation; sequence-dependent set-up times; SYMBIOTIC EVOLUTIONARY ALGORITHM; COLONY OPTIMIZATION ALGORITHM; UNRELATED PARALLEL MACHINES; TABU SEARCH HEURISTICS; MULTIOBJECTIVE OPTIMIZATION; GENETIC ALGORITHM; MAKESPAN; SYSTEM; MINIMIZE; MODEL;
D O I
10.1080/00207543.2015.1098786
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In job-shop scheduling, the importance of set-up issues is well known and has been considered in many solution approaches. However, in integrated process planning and scheduling (IPPS) involving flexible process plans, the set-up times are often ignored, or absorbed into processing times in IPPS domain, with the purpose to reduce the complexity. This is based on the assumption that set-up times are sequence-independent, or short enough to be ignored compared to processing times. However, it is not uncommon to encounter sequence-dependent set-up times (SDSTs) in practical production. This paper conducts a detailed investigation on the impact of SDSTs on the practical performance of the schedule: a comparative study is made for different cases where set-up times are (1) separately considered, (2) absorbed into processing times, or (3) totally ignored. An enhanced version of ant colony optimisation (E-ACO) algorithm is used to solve the IPPS problem, with the objective to minimise the total makespan. The following four types of set-up issues are considered: part loading/unloading, fixture preparation, tool switching and material transportation. Situations with various set-up time lengths have been studied and compared. A special case of IPPS problem involving a large number of identical jobs has been specifically studied and discussed. The results have shown that, set-up times should be carefully dealt with under different circumstances.
引用
收藏
页码:4815 / 4838
页数:24
相关论文
共 57 条
[1]   A PSO and a Tabu search heuristics for the assembly scheduling problem of the two-stage distributed database application [J].
Allahverdi, A ;
Al-Anzi, FS .
COMPUTERS & OPERATIONS RESEARCH, 2006, 33 (04) :1056-1080
[2]   A review of scheduling research involving setup considerations [J].
Allahverdi, A ;
Gupta, JND ;
Aldowaisan, T .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1999, 27 (02) :219-239
[3]   The significance of reducing setup times/setup costs [J].
Allahverdi, Ali ;
Soroush, H. M. .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 187 (03) :978-984
[4]  
[Anonymous], 2012, Int. J. Math. Anal
[5]  
[Anonymous], INT J EMERGING TECHN
[6]   A two-stage Ant Colony optimization algorithm to minimize the makespan on unrelated parallel machines-part II: enhancements and experimentations [J].
Arnaout, Jean-Paul ;
Musa, Rami ;
Rabadi, Ghaith .
JOURNAL OF INTELLIGENT MANUFACTURING, 2014, 25 (01) :43-53
[7]   A two-stage Ant Colony Optimization algorithm to minimize the makespan on unrelated parallel machines with sequence-dependent setup times [J].
Arnaout, Jean-Paul ;
Rabadi, Ghaith ;
Musa, Rami .
JOURNAL OF INTELLIGENT MANUFACTURING, 2010, 21 (06) :693-701
[8]   A simulated annealing-based multiobjective optimization algorithm: AMOSA [J].
Bandyopadhyay, Sanghamitra ;
Saha, Sriparna ;
Maulik, Ujjwal ;
Deb, Kalyanmoy .
IEEE TRANSACTIONS ON EVOLUTIONARY COMPUTATION, 2008, 12 (03) :269-283
[9]   Scheduling optimization of flexible manufacturing system using cuckoo search-based approach [J].
Burnwal, Shashikant ;
Deb, Sankha .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2013, 64 (5-8) :951-959
[10]   Operating room planning and scheduling: A literature review [J].
Cardoen, Brecht ;
Demeulemeester, Erik ;
Belien, Jeroen .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2010, 201 (03) :921-932