TIME-STEPPED, SIMULATION-BASED SCHEDULING SYSTEM FOR LARGE-SCALE INDUSTRIAL CONSTRUCTION PROJECTS

被引:0
作者
Hu, Di [1 ]
Mohamed, Yasser [1 ]
机构
[1] Univ Alberta, Dept Civil & Environm Engn, Hole Sch Construct Engn & Management, Markin CNRL Nat Resources Engn Facil, Edmonton, AB T6G 2W2, Canada
来源
2013 WINTER SIMULATION CONFERENCE (WSC) | 2013年
关键词
OPTIMIZATION; SPACE; MODEL;
D O I
暂无
中图分类号
TP301 [理论、方法];
学科分类号
081202 ;
摘要
Industrial construction projects have recently moved more towards tighter schedules and fast-tracked engineering and construction. This leads to overlap between work packages, increased occurrences of resource over-allocation and site congestion, which pose challenges to project planners in scheduling construction works and dynamically allocating resources considering the construction site conditions. Most previous research related to scheduling and resource allocation assumes that allocated resources remain consistent throughout the execution of work packages. This paper presents a workface planning system that allows for variable resource allocation and variable durations in execution of a work package, while holding logic relationships and space congestion constraints. A case study from a real industrial project is presented and results show that the proposed system reduces resource idle time as well as returns shorter project duration than traditional scheduling approaches.
引用
收藏
页码:3249 / 3256
页数:8
相关论文
共 50 条
  • [31] Large-Scale Real-Time Hybrid Simulation for Evaluation of Advanced Damping System Performance
    Friedman, Anthony
    Dyke, Shirley J.
    Phillips, Brian
    Ahn, Ryan
    Dong, Baiping
    Chae, Yunbyeong
    Castaneda, Nestor
    Jiang, Zhaoshuo
    Zhang, Jianqiu
    Cha, Youngjin
    Ozdagli, Ali Irmak
    Spencer, B. F.
    Ricles, James
    Christenson, Richard
    Agrawal, Anil
    Sause, Richard
    JOURNAL OF STRUCTURAL ENGINEERING, 2015, 141 (06)
  • [32] Sensor-fused simulation-based decision support system for earthmoving projects
    Zamani, Vahid
    Taghaddos, Hosein
    Gholipour, Yaghob
    AUTOMATION IN CONSTRUCTION, 2023, 156
  • [33] A Reinforcement Learning Based Large-Scale Refinery Production Scheduling Algorithm
    Chen, Yuandong
    Ding, Jinliang
    Chen, Qingda
    IEEE TRANSACTIONS ON AUTOMATION SCIENCE AND ENGINEERING, 2024, 21 (04) : 6041 - 6055
  • [34] Exploring Plan-Based Scheduling for Large-Scale Computing Systems
    Zheng, Xingwu
    Zhou, Zhou
    Yang, Xu
    Lan, Zhiling
    Wang, Jia
    2016 IEEE INTERNATIONAL CONFERENCE ON CLUSTER COMPUTING (CLUSTER), 2016, : 259 - 268
  • [35] A Knowledge Transfer Based Scheduling Algorithm for Large-Scale Refinery Production
    Chen, Yuandong
    Ding, Jinliang
    Chai, Tianyou
    IEEE TRANSACTIONS ON INDUSTRIAL INFORMATICS, 2022, 18 (02) : 869 - 879
  • [36] Optimisation of construction site layout using a hybrid simulation-based system
    Zhou, F.
    AbouRizk, S. M.
    Al-Battaineh, H.
    SIMULATION MODELLING PRACTICE AND THEORY, 2009, 17 (02) : 348 - 363
  • [37] Multiproject Time-cost Trade-off Scheduling Problem for Large-scale Construction Systems under Fuzzy Uncertainty
    Ouyang Yong-liu
    Zhang Meng-xiang
    Han Lu
    Lu Yi
    2015 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING - 22ND ANNUAL CONFERENCE PROCEEDINGS, VOLS I AND II, 2015, : 282 - 292
  • [38] A Multitime Window Parallel Scheduling System for Large-Scale Offshore Platform Project
    Yang, Boxin
    Yin, Wenhao
    Li, Jinghua
    Zhou, Qinghua
    WIRELESS COMMUNICATIONS & MOBILE COMPUTING, 2022, 2022
  • [39] Research on optimal self-scheduling horizon for the wind power and large-scale CAES combined system
    Li, Yaowang
    Miao, Shihong
    Yin, Binxin
    Liu, Junyao
    Yang, Weichen
    Zhang, Songyan
    IET GENERATION TRANSMISSION & DISTRIBUTION, 2019, 13 (22) : 5197 - 5206
  • [40] A Large-Scale Study of the Time Required to Compromise a Computer System
    Holm, Hannes
    IEEE TRANSACTIONS ON DEPENDABLE AND SECURE COMPUTING, 2014, 11 (01) : 2 - 15