A Statistical Comparison of Metaheuristics for Unrelated Parallel Machine Scheduling Problems with Setup Times

被引:6
作者
Antunes, Ana Rita [1 ]
Matos, Marina A. [1 ]
Rocha, Ana Maria A. C. [1 ]
Costa, Lino A. [1 ]
Varela, Leonilde R. [1 ]
机构
[1] Univ Minho, ALGORITMI Ctr, P-4710057 Braga, Portugal
关键词
scheduling; unrelated parallel machines; sequence-dependent tasks; makespan; metaheuristics; genetic algorithm; statistical analysis; COLONY OPTIMIZATION ALGORITHM; DIFFERENTIAL EVOLUTION; GENETIC ALGORITHM; MAKESPAN; MINIMIZE; TARDINESS;
D O I
10.3390/math10142431
中图分类号
O1 [数学];
学科分类号
0701 ; 070101 ;
摘要
Manufacturing scheduling aims to optimize one or more performance measures by allocating a set of resources to a set of jobs or tasks over a given period of time. It is an area that considers a very important decision-making process for manufacturing and production systems. In this paper, the unrelated parallel machine scheduling problem with machine-dependent and job-sequence-dependent setup times is addressed. This problem involves the scheduling of tasks on unrelated machines with setup times in order to minimize the makespan. The genetic algorithm is used to solve small and large instances of this problem when processing and setup times are balanced (Balanced problems), when processing times are dominant (Dominant P problems), and when setup times are dominant (Dominant S problems). For small instances, most of the values achieved the optimal makespan value, and, when compared to the metaheuristic ant colony optimization (ACOII) algorithm referred to in the literature, it was found that there were no significant differences between the two methods. However, in terms of large instances, there were significant differences between the optimal makespan obtained by the two methods, revealing overall better performance by the genetic algorithm for Dominant S and Dominant P problems.
引用
收藏
页数:19
相关论文
共 56 条
[1]   A Hybrid Genetic Algorithm for solving the Unrelated Parallel Machine Scheduling problem with Sequence Dependent Setup Times [J].
Abreu, L. R. ;
Prata, B. A. .
IEEE LATIN AMERICA TRANSACTIONS, 2018, 16 (06) :1715-1722
[2]   The third comprehensive survey on scheduling problems with setup times/costs [J].
Allahverdi, Ali .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 246 (02) :345-378
[3]  
Amaral Gabriela, 2020, Hybrid Intelligent Systems. 18th International Conference on Hybrid Intelligent Systems (HIS 2018). Advances in Intelligent Systems and Computing (AISC 923), P398, DOI 10.1007/978-3-030-14347-3_39
[4]  
Andre Serrae Santos., 2015, International Journal of Industrial Engineering Computations, V6, P145
[5]  
[Anonymous], SCHEDULING RES VIRTU
[6]   A worm optimization algorithm to minimize the makespan on unrelated parallel machines with sequence-dependent setup times [J].
Arnaout, Jean-Paul .
ANNALS OF OPERATIONS RESEARCH, 2020, 285 (1-2) :273-293
[7]   A two-stage Ant Colony optimization algorithm to minimize the makespan on unrelated parallel machines-part II: enhancements and experimentations [J].
Arnaout, Jean-Paul ;
Musa, Rami ;
Rabadi, Ghaith .
JOURNAL OF INTELLIGENT MANUFACTURING, 2014, 25 (01) :43-53
[8]   A two-stage Ant Colony Optimization algorithm to minimize the makespan on unrelated parallel machines with sequence-dependent setup times [J].
Arnaout, Jean-Paul ;
Rabadi, Ghaith ;
Musa, Rami .
JOURNAL OF INTELLIGENT MANUFACTURING, 2010, 21 (06) :693-701
[9]  
Artiba A., 1996, The Planning and Scheduling of Production Systems: Methodologies and Applications, DOI [DOI 10.1007/978-1-4613-1195-9, 10.1007/978-1-4613-1195-9]
[10]   Minimising maximum tardiness in assembly flowshops with setup times [J].
Aydilek, Asiye ;
Aydilek, Harun ;
Allahverdi, Ali .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2017, 55 (24) :7541-7565