A genetic algorithm approach to a general category project scheduling problem

被引:116
|
作者
Özdamar, L [1 ]
机构
[1] Istanbul Kultur Univ, Dept Comp Engn, TR-80280 Istanbul, Turkey
来源
IEEE TRANSACTIONS ON SYSTEMS MAN AND CYBERNETICS PART C-APPLICATIONS AND REVIEWS | 1999年 / 29卷 / 01期
关键词
genetic algorithms; heuristic knowledge; resource-constrained project scheduling;
D O I
10.1109/5326.740669
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
A genetic algorithm (GA) approach is proposed for the general resource constrained project scheduling model, in which activities may be executed in more than one operating mode and renewable as well as nonrenewable resource constraints exist, Each activity operation mode has a different duration and requires different amounts of renewable and nonrenewable resources. The objective is the minimization of the project duration or makespan, The problem under consideration is known to be one of the most difficult scheduling problems, and it is hard to find a feasible solution for such a problem, let alone the optimal one, The GA approach described here incorporates problem-specific scheduling knowledge by an indirect chromosome encoding that consists of selected activity operating modes and an ordered set of scheduling rules, The scheduling rules in the chromosome are used in an iterative scheduling algorithm that constructs the schedule resulting from the chromosome. The proposed GA is denoted as a hybrid GA (HGA) approach since it is integrated with traditional scheduling tools and expertise specifically developed for the general resource constrained project scheduling problem. The results demonstrate that HGA approach produces near-optimal solutions within a reasonable amount of computation time.
引用
收藏
页码:44 / 59
页数:16
相关论文
共 50 条
  • [21] A genetic algorithm for the project assignment problem
    Harper, PR
    de Senna, V
    Vieira, IT
    Shahani, AK
    COMPUTERS & OPERATIONS RESEARCH, 2005, 32 (05) : 1255 - 1265
  • [22] A Neurogenetic approach for the resource-constrained project scheduling problem
    Agarwal, Anurag
    Colak, Selcuk
    Erenguc, Selcuk
    COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 44 - 50
  • [23] A genetic algorithm approach to system scheduling
    Todd, DS
    Scott, JA
    Sen, P
    LARGE SCALE SYSTEMS: THEORY AND APPLICATIONS 1998 (LSS'98), VOL 1, 1999, : 277 - 282
  • [24] A genetic algorithm with resource buffers for the resource-constrained multi-project scheduling problem
    Bredael, Dries
    Vanhoucke, Mario
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2024, 315 (02) : 19 - 34
  • [25] A Genetic Algorithm for a Workforce Scheduling and Routing Problem
    Algethami, Haneen
    Pinheiro, Rodrigo Lankaites
    Landa-Silva, Dario
    2016 IEEE CONGRESS ON EVOLUTIONARY COMPUTATION (CEC), 2016, : 927 - 934
  • [26] A production scheduling problem using genetic algorithm
    Knosala, R
    Wal, T
    JOURNAL OF MATERIALS PROCESSING TECHNOLOGY, 2001, 109 (1-2) : 90 - 95
  • [27] Aircraft Category Based Genetic Algorithm for Aircraft Arrival Sequencing and Scheduling
    Meng Xiangwei
    Zhang Ping
    Li Chunjin
    PROCEEDINGS OF THE 29TH CHINESE CONTROL CONFERENCE, 2010, : 5188 - 5193
  • [28] Hybrid Genetic Algorithm with Simulated Annealing for Resource-Constrained Project Scheduling
    Bettemir, Onder Halis
    Sonmez, Rifat
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2015, 31 (05)
  • [29] An equitable approach to the payment scheduling problem in project management
    Ulusoy, G
    Cebelli, S
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2000, 127 (02) : 262 - 278
  • [30] A hybrid genetic algorithm for the early/tardy scheduling problem
    Valente, Jorge M. S.
    Goncalves, Jose Fernando
    Alves, Rui A. F. S.
    ASIA-PACIFIC JOURNAL OF OPERATIONAL RESEARCH, 2006, 23 (03) : 393 - 405