Multicomponent Maintenance Optimization: A Stochastic Programming Approach

被引:13
作者
Zhu, Zhicheng [1 ]
Xiang, Yisha [1 ]
Zeng, Bo [2 ]
机构
[1] Texas Tech Univ, Dept Ind Mfg & Syst Engn, Lubbock, TX 79409 USA
[2] Univ Pittsburgh, Dept Ind Engn, Pittsburgh, PA 15261 USA
基金
美国国家科学基金会;
关键词
maintenance optimization; multicomponent system; stochastic programming; progressive hedging algorithm; heuristic; INTEGER PROGRAMS; DECISION-MAKING; MODELS; POLICY; REPLACEMENT; SYSTEMS; STRATEGIES;
D O I
10.1287/ijoc.2020.0997
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Maintenance optimization has been extensively studied in the past decades. However, most of the existing maintenance models focus on single-component systems and are not applicable to complex systems consisting of multiple components, due to various interactions among the components. The multicomponent maintenance optimization problem, which joins the stochastic processes regarding the failures of components with the combinatorial problems regarding the grouping of maintenance activities, is challenging in both modeling and solution techniques, and has remained an open issue in the literature. In this paper, we study the multicomponent maintenance problem over a finite planning horizon and formulate the problem as a multistage stochastic integer program with decision-dependent uncertainty. There is a lack of general efficient methods to solve this type of problem. To address this challenge, we use an alternative approach to model the underlying failure process and develop a novel two-stage model without decision-dependent uncertainty. Structural properties of the two-stage problem are investigated, and a progressive-hedging-based heuristic is developed based on the structural properties. Our heuristic algorithm demonstrates a significantly improved capacity to handle large-size two-stage problems comparing to three conventional methods for stochastic integer programming, and solving the two-stage model by our heuristic in a rolling horizon provides a good approximation of the multistage problem. The heuristic is further benchmarked with a dynamic programming approach and a structural policy, which are two commonly adopted approaches in the literature. Numerical results show that our heuristic can lead to significant cost savings compared with the benchmark approaches.
引用
收藏
页码:898 / 914
页数:17
相关论文
共 43 条
  • [1] Medium-term maintenance turnaround planning under uncertainty for integrated chemical sites
    Amaran, Satyajith
    Zhang, Tong
    Sahinidis, Nikolaos V.
    Sharda, Bikram
    Bury, Scott J.
    [J]. COMPUTERS & CHEMICAL ENGINEERING, 2016, 84 : 422 - 433
  • [2] Models and computational strategies for multistage stochastic programming under endogenous and exogenous uncertainties
    Apap, Robert M.
    Grossmann, Ignacio E.
    [J]. COMPUTERS & CHEMICAL ENGINEERING, 2017, 103 : 233 - 274
  • [3] Aydin N., 2012, PhD Thesis
  • [4] Simulation modelling of repairable multi-component deteriorating systems for 'on condition' maintenance optimisation
    Barata, J
    Soares, CG
    Marseguerra, M
    Zio, E
    [J]. RELIABILITY ENGINEERING & SYSTEM SAFETY, 2002, 76 (03) : 255 - 264
  • [5] Short-term electricity procurement: A rolling horizon stochastic programming approach
    Beraldi, Patrizia
    Violi, Antonio
    Scordino, Nadia
    Sorrentino, Nicola
    [J]. APPLIED MATHEMATICAL MODELLING, 2011, 35 (08) : 3980 - 3990
  • [6] Birge JR, 2011, SPRINGER SER OPER RE, P3, DOI 10.1007/978-1-4614-0237-4
  • [7] Strengthened Benders Cuts for Stochastic Integer Programs with Continuous Recourse
    Bodur, Merve
    Dash, Sanjeeb
    Gunluk, Oktay
    Luedtke, James
    [J]. INFORMS JOURNAL ON COMPUTING, 2017, 29 (01) : 77 - 91
  • [8] A condition-based maintenance policy with non-periodic inspections for a two-unit series system
    Castanier, B
    Grall, A
    Bérenguer, C
    [J]. RELIABILITY ENGINEERING & SYSTEM SAFETY, 2005, 87 (01) : 109 - 120
  • [9] Dynamic modeling of the tradeoff between productivity and safety in critical engineering systems
    Cowing, MM
    Paté-Cornell, ME
    Glynn, PW
    [J]. RELIABILITY ENGINEERING & SYSTEM SAFETY, 2004, 86 (03) : 269 - 284
  • [10] Joint replacement in an operational planning phase
    Dekker, R
    Wildeman, RE
    vanEgmond, R
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 91 (01) : 74 - 88