Proactive policies for the stochastic resource-constrained project scheduling problem

被引:103
作者
Deblaere, Filip [1 ]
Demeulemeester, Erik [1 ]
Herroelen, Willy [1 ]
机构
[1] Katholieke Univ Leuven, Fac Business & Econ, Res Ctr Operat Management, B-3000 Louvain, Belgium
关键词
Project scheduling; Proactive scheduling; Execution policies; Stochastic RCPSP;
D O I
10.1016/j.ejor.2011.04.019
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
The resource-constrained project scheduling problem involves the determination of a schedule of the project activities, satisfying the precedence and resource constraints while minimizing the project duration. In practice, activity durations may be subject to variability. We propose a stochastic methodology for the determination of a project execution policy and a vector of predictive activity starting times with the objective of minimizing a cost function that consists of the weighted expected activity starting time deviations and the penalties or bonuses associated with late or early project completion. In a computational experiment, we show that our procedure greatly outperforms existing algorithms described in the literature. (C) 2011 Elsevier B.V. All rights reserved.
引用
收藏
页码:308 / 316
页数:9
相关论文
共 26 条
[11]   A BRANCH-AND-BOUND PROCEDURE FOR THE MULTIPLE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM [J].
DEMEULEMEESTER, E ;
HERROELEN, W .
MANAGEMENT SCIENCE, 1992, 38 (12) :1803-1818
[12]   New benchmark results for the resource - Constrained project scheduling problem [J].
Demeulemeester, EL ;
Herroelen, WS .
MANAGEMENT SCIENCE, 1997, 43 (11) :1485-1492
[13]   COMPUTATIONAL-COMPLEXITY OF PERT PROBLEMS [J].
HAGSTROM, JN .
NETWORKS, 1988, 18 (02) :139-147
[14]  
Herroelen W., 2000, EUR J OPER RES, V128, P221
[15]   PSPLIB - A project scheduling problem library [J].
Kolisch, R ;
Sprecher, A .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1997, 96 (01) :205-216
[16]  
Lambrechts O, 2007, THESIS KU LEUVEN
[17]   A tabu search procedure for developing robust predictive project schedules [J].
Lambrechts, Olivier ;
Demeulemeester, Erik ;
Herroelen, Willy .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2008, 111 (02) :493-508
[18]   Proactive and reactive strategies for resource-constrained project scheduling with uncertain resource availabilities [J].
Lambrechts, Olivier ;
Demeulemeester, Erik ;
Herroelen, Willy .
JOURNAL OF SCHEDULING, 2008, 11 (02) :121-136
[19]   Stability and resource allocation in project planning [J].
Leus, R ;
Herroelen, W .
IIE TRANSACTIONS, 2004, 36 (07) :667-682
[20]  
Mohring R. H., 1984, Zeitschrift fur Operations Research, Serie A (Theorie), V28, P193, DOI 10.1007/BF01919323