Scheduling resource-constrained project problem with alternative activity chains

被引:40
作者
Tao, Sha [1 ]
Dong, Zhijie Sasha [2 ]
机构
[1] Nanjing Univ, Dept Management & Engn, Nanjing 210093, Jiangsu, Peoples R China
[2] Texas State Univ, Ind Engn Program, Ingram Sch Engn, San Marcos, TX 78666 USA
关键词
Resource-constrained project scheduling; Activity chains; Project scheduling problem; AND-OR network; Extended simulated annealing; ANT COLONY OPTIMIZATION; ALGORITHM;
D O I
10.1016/j.cie.2017.10.027
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
This research introduces a problem called resource-constrained project scheduling problem with alternative activity chains, which is inspired from project scheduling practice. An AND-OR project network representation is designed for the problem and then an integer linear program is developed. An extended simulated annealing algorithm is proposed to solve the large-scale problem efficiently, which consists of new activity-selection list solution presentation, schedule generation scheme and neighbor generation mechanism. Computational experiments are carried out to validate the proposed model and to evaluate the performance of the proposed algorithm.
引用
收藏
页码:288 / 296
页数:9
相关论文
共 50 条
  • [41] A three-dimensional spatial resource-constrained project scheduling problem: Model and heuristic
    Zhang, Jingwen
    Li, Lubo
    Demeulemeester, Erik
    Zhang, Haohua
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2024, 319 (03) : 943 - 966
  • [42] Resource-constrained project scheduling problem with multiple execution modes and fuzzy/crisp activity durations
    Atli, Omer
    Kahraman, Cengiz
    JOURNAL OF INTELLIGENT & FUZZY SYSTEMS, 2014, 26 (04) : 2001 - 2020
  • [43] A memetic algorithm to address the multi-node resource-constrained project scheduling problem
    Machado-Dominguez, Luis F.
    Paternina-Arboleda, Carlos D.
    Velez, Jorge, I
    Barrios-Sarmiento, Agustin
    JOURNAL OF SCHEDULING, 2021, 24 (04) : 413 - 429
  • [44] A new scheduling technique for the resource-constrained project scheduling problem with discounted cash flows
    Leyman, Pieter
    Vanhoucke, Mario
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2015, 53 (09) : 2771 - 2786
  • [45] A priority rule for scheduling shared due dates in the resource-constrained project scheduling problem
    Strahl, William R.
    Gounaris, Chrysanthos E.
    COMPUTERS & INDUSTRIAL ENGINEERING, 2023, 183
  • [46] NONPREEMPTIVE MULTIMODE RESOURCE-CONSTRAINED PROJECT SCHEDULING
    DREXL, A
    GRUENEWALD, J
    IIE TRANSACTIONS, 1993, 25 (05) : 74 - 81
  • [47] Robust optimization for resource-constrained project scheduling with uncertain activity durations
    Artigues, Christian
    Leus, Roel
    Nobibon, Fabrice Talla
    FLEXIBLE SERVICES AND MANUFACTURING JOURNAL, 2013, 25 (1-2) : 175 - 205
  • [48] Robust optimization for resource-constrained project scheduling with uncertain activity durations
    Leus, R.
    Artigues, C.
    Nobibon, F. Talla
    2011 IEEE INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND ENGINEERING MANAGEMENT (IEEM), 2011, : 101 - 105
  • [49] Ant Colony Optimization for Multimode Resource-Constrained Project Scheduling
    Zhang, Hong
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2012, 28 (02) : 150 - 159
  • [50] Approximability results for the resource-constrained project scheduling problem with a single type of resources
    Gafarov, Evgeny R.
    Lazarev, Alexander A.
    Werner, Frank
    ANNALS OF OPERATIONS RESEARCH, 2014, 213 (01) : 115 - 130