Calculation of pile-soil stress in pile-net composite foundation based on improved Terzarghi method

被引:0
作者
Huang Yu-hua [1 ]
Xu Lin-rong [1 ,2 ]
Zhou Jun-jie [1 ]
Cai Yu [1 ]
机构
[1] Cent South Univ, Sch Civil Engn, Changsha 410075, Hunan, Peoples R China
[2] Cent South Univ, Natl Engn Lab High Speed Railway Construct, Changsha 410075, Hunan, Peoples R China
基金
中国国家自然科学基金;
关键词
pile-net composite foundation; pile-soil stress ratio; soil arching effect; membrane effect; time-varying characteristics; EARTH PRESSURE; RATIO;
D O I
10.16285/j.rsm.2019.0050
中图分类号
P5 [地质学];
学科分类号
0709 ; 081803 ;
摘要
The pile-soil stress ratio is an important parameter for calculating the bearing capacity and settlement of the pile-net composite foundation, which is related to the consolidation settlement of the foundation and has obvious time-varying characteristics. The calculation theory of loosening earth pressure based on Terzarghi soil arch model is discussed on the assumption that the soil of sliding surface reaches limit state, and it is not suitable for the calculation of pile-soil stress under the condition of small deformation of pile-net foundation. Therefore, on the basis of Terzarghi model, the equivalent stiffness ideal elastic-plastic model is adopted for the transfer function of relative displacement surface, and the theoretical solutions of pile-soil stress and soil arch height are derived by combining the equilibrium equation of soil element with the deformation coordination equation. The quantitative variation of pile-soil stress and the membrane effect with each design parameter is analyzed systematically. The results show that the improved method is more applicable than the existing arching algorithm model. With the increase of pile-soil differential settlement, the arching height and pile-soil stress ratio gradually increased, and the arching ratio decreased in hyperbolic shape, while the membrane effect works gradually. The arching effect is significantly weakened by increasing the filling load, and the pile-soil stress ratio decreases with the increase of pile spacing and increases with the increase of cohesive force. Based on the improved method and the field measured data, the time-varying characteristics of pile-soil stress are analyzed, and the rationality of the method is verified. The method proposed can be used as a reference for the calculation of pile-soil stress on the pile-netted foundation.
引用
收藏
页码:667 / 675
页数:9
相关论文
共 29 条
[1]   A simplified method for analysis of a piled embankment reinforced with geosynthetics [J].
Abusharar, Sari W. ;
Zheng, Jun-Jie ;
Chen, Bao-Guo ;
Yin, Jian-Hua .
GEOTEXTILES AND GEOMEMBRANES, 2009, 27 (01) :39-52
[2]  
Chen RX, 2010, ROCK SOIL MECH, V31, P1402
[3]  
[陈云敏 Chen Yunmin], 2004, [中国公路学报, China Journal of Highway and Transport], V17, P1
[4]   THE ARCH IN SOIL ARCHING [J].
HANDY, RL .
JOURNAL OF GEOTECHNICAL ENGINEERING-ASCE, 1985, 111 (03) :302-318
[5]  
Hewlett W.J., 1988, Ground Engineering, V21, P12
[6]  
IGLESIA G R, 2013, J GEOTECHNICAL GEOEN, V140
[7]   Stress Analysis of CFG Pile Composite Foundation in Consolidating Saturated Mine Tailings Dam [J].
Lai, Jinxing ;
Liu, Houquan ;
Qiu, Junling ;
Fan, Haobo ;
Zhang, Qian ;
Hu, Zhinan ;
Wang, Junbao .
ADVANCES IN MATERIALS SCIENCE AND ENGINEERING, 2016, 2016
[8]  
Li RL, 2017, ROCK SOIL MECH, V38, P3145, DOI 10.16285/j.rsm.2017.11.009
[9]  
[刘汉龙 Liu Hanlong], 2016, [土木工程学报, China Civil Engineering Journal], V49, P96
[10]  
[刘吉福 Liu Jifu], 2003, [岩石力学与工程学报, Chinese Journal of Rock Mechanics and Engineering], V22, P674