AN IMPROVED TIME-COST TRADE-OFF MODEL WITH OPTIMAL LABOR PRODUCTIVITY

被引:10
作者
Lin, Chien-Liang [1 ]
Lai, Yu-Che [1 ]
机构
[1] Natl Kaohsiung Univ Sci & Technol, Dept Construct Engn, Kaohsiung, Taiwan
关键词
labor productivity; time-cost trade-off; optimization; genetic algorithm; CONSTRUCTION; OPTIMIZATION; DESIGN; ACCELERATION;
D O I
10.3846/jcem.2020.11663
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Optimization of the time-cost trade off (TCT) has received considerable attention for several decades. However, few studies have considered improving performance/productivity of existing crews. To shorten the gap to real-world applications, this study presents an improved TCT model that considers variable productivity using genetic algorithms (GAs). Through an illustrative case and a real world case, the results demonstrate that improving labor productivity of selected activities by allocating existing crews and management can yield an optimized solution. As such, a decision maker can implement a better optimized technique to reduce a project duration under budget while reducing the risk of liquidated damages. The main contribution of this study is to apply managerial improvement of labor productivity to TCT optimization, the project duration can be reduced owing to improved productivity of existing crews rather than inefficient overmanning, overlapping or costly substitution. In the end, three important managerial insights are presented and future research is recommended.
引用
收藏
页码:113 / 130
页数:18
相关论文
共 35 条
[1]   Optimizing the Scheduling of Repetitive Construction to Minimize Interruption Cost [J].
Altuwaim, Ayman ;
El-Rayes, Khaled .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (07)
[2]  
[Anonymous], 2011, Anti-dysmenorrhea components from the rhizomes of Cyperus rotundus Linn. (Cyperaceae)
[3]  
Berthaut F, 2011, CIRRELT201109
[4]   Construction resource scheduling with genetic algorithms [J].
Chan, WT ;
Chua, DKH ;
Kannan, G .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (02) :125-132
[5]   Hybrid of genetic algorithm and simulated annealing for multiple project scheduling with multiple resource constraints [J].
Chen, Po-Han ;
Shahandashti, Seyed Mohsen .
AUTOMATION IN CONSTRUCTION, 2009, 18 (04) :434-443
[6]   Time and Cost-Optimized Decision Support Model for Fast-Track Projects [J].
Cho, Kyuman ;
Hastak, Makarand .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2013, 139 (01) :90-101
[7]   Quantifying the impact of cost-based incentives on the performance of building projects in the United States [J].
Chokor A. ;
El Asmar M. ;
Paladugu B.S. .
Practice Periodical on Structural Design and Construction, 2017, 22 (02)
[8]   Optimization of overlapping activities in the design phase of construction projects [J].
Dehghan, Reza ;
Hazini, Kamran ;
Ruwanpura, Janaka .
AUTOMATION IN CONSTRUCTION, 2015, 59 :81-95
[9]   Factors Influencing Construction Labor Productivity in Egypt [J].
El-Gohary, Khaled Mahmoud ;
Aziz, Remon Fayek .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2014, 30 (01) :1-9
[10]   Time-cost-quality trade-off analysis for highway construction [J].
El-Rayes, K ;
Kandil, A .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2005, 131 (04) :477-486