An algorithm for a no-wait flowshop scheduling problem for minimizing total tardiness with a constraint on total completion time

被引:12
作者
Allahverdi, Ali [1 ]
Aydilek, Harun [2 ]
Aydilek, Asiye [3 ]
机构
[1] Kuwait Univ, Ind & Management Syst Engn Dept, Kuwait, Kuwait
[2] Gulf Univ Sci & Technol, Dept Math & Nat Sci, Kuwait, Kuwait
[3] Gulf Univ Sci & Technol, Dept Econ & Finance, Kuwait, Kuwait
关键词
Algorithm; Scheduling; Statistical analysis; No-wait; SWARM OPTIMIZATION ALGORITHM; MAKESPAN; HEURISTICS; MINIMIZATION; CRITERIA; SUBJECT; SEARCH;
D O I
10.5267/j.ijiec.2021.8.003
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We consider a no-wait m-machine flowshop scheduling problem which is common in different manufacturing industries such as steel, pharmaceutical, and chemical. The objective is to minimize total tardiness since it minimizes penalty costs and loss of customer goodwill. We also consider the performance measure of total completion time which is significant in environments where reducing holding cost is important. We consider both performance measures with the objective of minimizing total tardiness subject to the constraint that total completion time is bounded. Given that the problem is NP-hard, we propose an algorithm. We conduct extensive computational experiments to compare the performance of the proposed algorithm with those of three well performing benchmark algorithms in the literature. Computational results indicate that the proposed algorithm reduces the error of the best existing benchmark algorithm by 88% under the same CPU times. The results are confirmed by extensive statistical analysis. Specifically, ANOVA analysis is conducted to justify the difference between the performances of the algorithms, and a test of hypothesis is performed to justify that the proposed algorithm is significantly better than the best existing benchmark algorithm with a significance level of 0.01. (c) 2022 by the authors; licensee Growing Science, Canada
引用
收藏
页码:43 / 50
页数:8
相关论文
共 34 条
[1]   New heuristics for m-machine no-wait flowshop to minimize total completion time [J].
Aldowaisan, T ;
Allahverdi, A .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2004, 32 (05) :345-352
[2]   MINIMIZING TOTAL TARDINESS IN NO-WAIT FLOWSHOPS [J].
Aldowaisan, Tariq ;
Allahverdi, Ali .
FOUNDATIONS OF COMPUTING AND DECISION SCIENCES, 2012, 37 (03) :149-162
[3]   No-wait flowshops with bicriteria of makespan and maximum lateness [J].
Allahverdi, A ;
Aldowaisan, T .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2004, 152 (01) :132-147
[4]   No-wait flowshop scheduling problem with separate setup times to minimize total tardiness subject to makespan [J].
Allahverdi, Ali ;
Aydilek, Harun ;
Aydilek, Asiye .
APPLIED MATHEMATICS AND COMPUTATION, 2020, 365
[5]   No-wait flowshop scheduling problem with two criteria; total tardiness and makespan [J].
Allahverdi, Ali ;
Aydilek, Harun ;
Aydilek, Asiye .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2018, 269 (02) :590-601
[6]   A survey of scheduling problems with no-wait in process [J].
Allahverdi, Ali .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2016, 255 (03) :665-686
[7]   The third comprehensive survey on scheduling problems with setup times/costs [J].
Allahverdi, Ali .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 246 (02) :345-378
[8]   Total completion time with makespan constraint in no-wait flowshops with setup times [J].
Allahverdi, Ali ;
Aydilek, Harun .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2014, 238 (03) :724-734
[9]   Algorithms for no-wait flowshops with total completion time subject to makespan [J].
Allahverdi, Ali ;
Aydilek, Harun .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2013, 68 (9-12) :2237-2251
[10]  
[Anonymous], 2013, INT J OPERATIONS RES, V10, P29