Fixing construction planning puzzle: multi-constraint technique and decision support system

被引:0
作者
Sriprasert, E [1 ]
Dawood, N [1 ]
机构
[1] Univ Teesside, Ctr Construct Innovat Res, Middlesbrough, Cleveland, England
来源
CONCURRENT ENGINEERING: ADVANCED DESIGN, PRODUCTION AND MANAGEMENT SYSTEMS | 2003年
关键词
D O I
暂无
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In complex and concurrent construction projects, reliable planning becomes a centre for effective co-ordination across upstream supply chains and downstream operations at the work face. Thousands of literatures in construction planning have been published over the past 50 years; introducing, testing, and implementing mountain of techniques and tools. However, they are very fragmented and have yet provided a universal system that suits the industry needs. To fix this puzzle, this paper revisits and classifies available construction planning techniques into seven major groups. All of them are then differentiated based upon underlying concepts, levels of planning, sets of concerned constraints, uncertainty handling approaches, visual representations, and optimisation techniques. The results lead to a design of an innovative technique called "Multi-constraint planning system" that encourages collaborative management of four constraints regarding physical, contract, resource, and information. To enable the implementation of the proposed technique, an integrated decision support system that incorporates web-based and mobile information management system, 4D-visualisation system, and evolutionary optimisation system is successfully developed and demonstrated in this paper. It is envisaged that the discussion and the system demonstration in this paper will pave a way towards a universal research and development for the next generation of planning system in construction.
引用
收藏
页码:813 / 823
页数:11
相关论文
共 35 条
  • [1] Efficient method for scheduling construction projects with resource constraints
    Abeyasinghe, M.Chelaka L.
    Greenwood, David J.
    Johansen, D.Eric
    [J]. 2001, Elsevier Science Ltd, Exeter, United Kingdom (19)
  • [2] Formalization and automation of time-space conflict analysis
    Akinci, B
    Fischen, M
    Levitt, R
    Carlson, R
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2002, 16 (02) : 124 - 134
  • [3] [Anonymous], P 1999 WINT SIM C PH
  • [4] [Anonymous], MODERN CONSTRUCTION
  • [5] Arditi d., 2002, Construction Management and Economics [online], V20, P353
  • [6] BALLARD G, 1996, P 4 ANN C INT GROUP
  • [7] Ballard H., 2000, The Last Planner System of Production Control
  • [8] CHERNEFF J, 1991, J COMPUT CIVIL ENG, V5, P64
  • [9] Dawood N., 2002, P CIB W78 C AARH DEN, P53
  • [10] DUNCAN WR, 1996, GUIDE PROJECT MANAGE