Task network-based project dynamic scheduling and schedule coordination

被引:13
作者
Hao, Qi [1 ]
Shen, Weiming [1 ]
Xue, Yunjiao [1 ]
Wang, Shuying [1 ]
机构
[1] Natl Res Council Canada, Ctr Comp Assisted Construct Technol, London, ON N6G 4X8, Canada
关键词
Resource-constrained project scheduling problem (RCPSP); Dynamic scheduling; Multi-project scheduling; Schedule coordination; Aircraft maintenance management; RESOURCE; CLASSIFICATION; HEURISTICS;
D O I
10.1016/j.aei.2010.07.001
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
The resource-constrained project scheduling problem (RCPSP) is an extensively explored area The existing RCPSP solutions tend to focus on single project scheduling problems without practical supports to address complex constraints, dynamic environments, and multi-project schedule coordination. This paper proposes a dynamic project scheduling algorithm based on partial task network heuristics. This algorithm takes time constraints. resource constraints, and particularly the changing task execution status into consideration To coordinate conflicting schedules of multiple projects, we proposed an interactive decision support process and developed new algorithms for conflict detection, conflict resolution, and impact analysis The proposed algorithms have been fully implemented and tested in a web-based aircraft maintenance management system and are being applied in construction for project scheduling and facilities maintenance management. Crown Copyright (C) 2010 Published by Elsevier Ltd All rights reserved.
引用
收藏
页码:417 / 427
页数:11
相关论文
共 22 条
[1]   Analysis of trends in construction research: 1985-2002 [J].
Abudayyeh, O ;
Dibert-DeYoung, A ;
Jaselskis, E .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2004, 130 (03) :433-439
[2]  
[Anonymous], MULTIDISCIPLINARY SC
[3]  
Berry P. M., 1994, Intelligent Systems Engineering, V3, P79, DOI 10.1049/ise.1994.0011
[4]  
Betts M., 1993, CONSTR MANAG ECON, V11, P221, DOI DOI 10.1080/01446199300000024
[5]   SCHEDULING SUBJECT TO RESOURCE CONSTRAINTS - CLASSIFICATION AND COMPLEXITY [J].
BLAZEWICZ, J ;
LENSTRA, JK ;
KAN, AHGR .
DISCRETE APPLIED MATHEMATICS, 1983, 5 (01) :11-24
[6]  
BROWN J, 1999, P INF DEC CONTR, P41
[7]   Resource-constrained project scheduling: Notation, classification, models, and methods [J].
Brucker, P ;
Drexl, A ;
Mohring, R ;
Neumann, K ;
Pesch, E .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 112 (01) :3-41
[8]  
Hao Q., 2010, CONSTR RES C 2010 IN, P470, DOI [DOI 10.1061/41109, 10.1061/41109(373)47, DOI 10.1061/41109(373)47]
[9]   Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem [J].
Hartmann, S ;
Kolisch, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2000, 127 (02) :394-407
[10]   Resource-constrained project scheduling: A survey of recent developments [J].
Herroelen, W ;
De Reyck, B ;
Demeulemeester, E .
COMPUTERS & OPERATIONS RESEARCH, 1998, 25 (04) :279-302