Product sequencing problem in Mixed-Model Assembly Line to minimize unfinished works

被引:32
作者
Kim, Siwon
Jeong, Bonju
机构
[1] LG CNS Co Ltd, Seoul, South Korea
[2] Yonsei Univ, Dept Informat & Ind Engn, Seoul 120749, South Korea
关键词
sequencing; Mixed-Model Assembly Line; Branch & Bound; local search;
D O I
10.1016/j.cie.2007.06.011
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
This study is concerned about how to optimize the input sequence of product models with sequence-dependent setup time in Mixed-Model Assembly Line (MMAL) using conveyor system. Usually MMAL consists of a number of stations linked by a conveyor belt and each station has a work zone limited by upstream and down stream boundaries. To avoid improper interference between operators in the adjacent stations and excess of machine moving range, operators are forced to complete their operations within their predetermined work zone. In this study, our goal is to determine the sequence of models for minimizing the total unfinished work within their work zone. A generalized formulation of the product sequencing problem in MMAL is presented. We developed an optimal procedure using Branch & Bound technique and a heuristic procedure using lower bound and local search. Experimental results show that the heuristic procedure provides reasonably good solutions with low computational costs. (c) 2007 Elsevier Ltd. All rights reserved.
引用
收藏
页码:206 / 214
页数:9
相关论文
共 12 条
[1]  
[Anonymous], COMPUTERS IND ENG
[2]  
Bolat A, 1997, NAV RES LOG, V44, P419, DOI 10.1002/(SICI)1520-6750(199708)44:5<419::AID-NAV2>3.0.CO
[3]  
2-7
[4]   SEQUENCING JOBS ON AN AUTOMOBILE ASSEMBLY-LINE - OBJECTIVES AND PROCEDURES [J].
BOLAT, A .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1994, 32 (05) :1219-1236
[5]  
Cheng LP, 1996, IIE TRANS, V28, P919
[6]   ALGORITHMS FOR SCHEDULING MULTILEVEL JUST-IN-TIME PRODUCTION SYSTEMS [J].
MILTENBURG, J ;
SINNAMON, G .
IIE TRANSACTIONS, 1992, 24 (02) :121-130
[7]  
MODEN Y, 1983, TOYOTA PRODUCTION SY
[8]   Designing a mixed-model assembly line to minimize the costs of idle and utility times [J].
Sarker, BR ;
Pan, HX .
COMPUTERS & INDUSTRIAL ENGINEERING, 1998, 34 (03) :609-628
[9]   LEVEL SCHEDULES FOR MIXED-MODEL, JUST-IN-TIME PROCESSES [J].
STEINER, G ;
YEOMANS, S .
MANAGEMENT SCIENCE, 1993, 39 (06) :728-735
[10]   MIXED-MODEL SEQUENCING TO MINIMIZE UTILITY WORK AND THE RISK OF CONVEYOR STOPPAGE [J].
TSAI, LH .
MANAGEMENT SCIENCE, 1995, 41 (03) :485-495