Scheduling of multi-product batch plants using reachability analysis of timed automata models

被引:0
|
作者
Subbiah, Subanatarajan [1 ]
Panek, Sebastian [1 ]
Engell, Sebastian [1 ]
Stursberg, Olaf [2 ]
机构
[1] Univ Dortmund, Proc Control Lab BCI AST, D-44221 Dortmund, Germany
[2] Tech Univ Munich, Ind Automat Syst EI LSR, Munich, Germany
来源
ICINCO 2007: PROCEEDINGS OF THE FOURTH INTERNATIONAL CONFERENCE ON INFORMATICS IN CONTROL, AUTOMATION AND ROBOTICS, VOL ICSO: INTELLIGENT CONTROL SYSTEMS AND OPTIMIZATION | 2007年
关键词
scheduling; timed automata; reachability analysis; multi-product batch plant;
D O I
暂无
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
Standard scheduling approaches in process industries are often based on algebraic problem formulations solved as MI(N)LP optimization problems to derive production schedules. To handle such problems techniques based on timed automata have emerged recently. This contribution reports on a successful application of a new modeling scheme to formulate scheduling problems in process industries as timed automata (TA) models and describes the solution technique to obtain schedules using symbolic reachability analysis. First, the jobs, resources and additional constraints are modeled as sets of synchronized timed automata. Then, the individual automata are composed by parallel composition to form a global automaton which has an initial location where no jobs have been started and at least one target location where all jobs have been finished. A cost optimal symbolic reachability analysis is performed on the composed automaton to derive schedules. The main advantage of this approach over other MILP techniques is the intuitive graphical and modular modeling and the ability to compute better solutions within reasonable computation time. This is illustrated by a case study.
引用
收藏
页码:141 / +
页数:2
相关论文
共 50 条
  • [21] Scheduling for batch processes based on clustering approximated timed reachability graphs
    Zhou, Jiazhong
    Lefebvre, Dimitri
    Li, Zhiwu
    ISA TRANSACTIONS, 2024, 152 : 290 - 298
  • [22] A Full Symbolic Reachability Analysis Algorithm of Timed Automata Based on BDD
    Zhang, Huiping
    Du, Junwei
    Cao, Ling
    Zhu, Guixin
    2015 IEEE 12TH INTERNATIONAL SYMPOSIUM ON AUTONOMOUS DECENTRALIZED SYSTEMS ISADS 2015, 2015, : 301 - 304
  • [23] A continuous-time formulation for scheduling multistage multi-product batch plants with non-identical parallel units
    Liu, Y
    Karimi, IA
    European Symposium on Computer-Aided Process Engineering-15, 20A and 20B, 2005, 20a-20b : 1165 - 1170
  • [24] Scheduling of a pipeless multi-product batch plant using mixed-integer programming combined with heuristics
    Panek, S
    Engell, S
    Lessner, C
    European Symposium on Computer-Aided Process Engineering-15, 20A and 20B, 2005, 20a-20b : 1033 - 1038
  • [25] Intermediate storage tank operation strategies in the production scheduling of multi-product batch processes
    Ha, JK
    Chang, HK
    Lee, ES
    Lee, IB
    Lee, BS
    Yi, GB
    COMPUTERS & CHEMICAL ENGINEERING, 2000, 24 (2-7) : 1633 - 1640
  • [26] Scheduling a multi-product pipeline network
    de Souza Filho, Erito Marques
    Bahiense, Laura
    Martins Ferreira Filho, Virgilio Jose
    COMPUTERS & CHEMICAL ENGINEERING, 2013, 53 : 55 - 69
  • [27] A novel MILP formulation for short-term scheduling of multi-stage multi-product batch plants with sequence-dependent constraints
    Hui, CW
    Gupta, A
    van der Meulen, HAJ
    COMPUTERS & CHEMICAL ENGINEERING, 2000, 24 (12) : 2705 - 2717
  • [28] Batch sizing in multi-stage, multi-product batch production systems
    Trautmann, Norbert
    Baumann, Philipp
    Saner, Nadine
    Schaefer, Tobias
    21ST EUROPEAN SYMPOSIUM ON COMPUTER AIDED PROCESS ENGINEERING, 2011, 29 : 905 - 909
  • [29] Capacity analysis of multi-product plants integrating energy consumption
    Oldenburg, N
    Gruhn, G
    Stoldt, J
    APPLIED THERMAL ENGINEERING, 2001, 21 (13-14) : 1283 - 1298
  • [30] MILP reformulations for the design of biotechnological multi-product batch plants using continuous equipment sizes and discrete host selection
    Sandoval, G.
    Espinoza, D.
    Figueroa, N.
    Asenjo, J. A.
    COMPUTERS & CHEMICAL ENGINEERING, 2016, 84 : 1 - 11