A TOPSIS-Risk Matrix and Monte Carlo Expert System for Risk Assessment in Engineering Projects

被引:19
作者
Koulinas, Georgios K. [1 ]
Demesouka, Olympia E. [1 ]
Sidas, Konstantinos A. [2 ]
Koulouriotis, Dimitrios E. [1 ]
机构
[1] Democritus Univ Thrace, Dept Prod & Management Engn, 12 Vas Sofias St, Xanthi 67100, Greece
[2] Hellen Open Univ, Fac Sci & Technol, Dept Engn Project Management, Parodos Aristotelous 18 St, Patras 26335, Greece
关键词
TOPSIS; risk matrix; schedule analysis; uncertainty; Monte Carlo Simulation; DECISION-MAKING; SUPPLY CHAIN; SAFETY;
D O I
10.3390/su132011277
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
In this paper, we propose a process that combines the Risk Matrix approach with the Technique for Order of Preference by Similarity to Ideal Solution (TOPSIS) and the Monte Carlo Simulation for assessing risk factors that have an impact on the duration of a construction project's activities and predict if it is feasible to terminate the project within the prescribed deadlines. Initially, we identified the risks affecting each task of the specific project, and then, we applied the risk matrix approach for determining the probability and impact of every risk to each activity. The resulting ranking is used to assign uncertainty to activities' durations and estimate the probability of on-time project completion, employing the Monte Carlo Simulation approach. The main contribution of this paper is the development of an innovative framework that coordinates an established qualitative and quantitative risk classification approach, with a popular multicriteria method and a powerful simulation approach, to effectively predict time deviations while executing complex construction projects under uncertainty. The proposed framework was applied to estimate the possibility of a timely execution of an artificial lake real project on the island of Alonissos, Greece. The analysis results illustrate that this approach clearly could help the project risk manager proactively perform risk mitigation measures while allocating budget and programming a project with a significant impact on the quality of life of residents and tourists of a small island.</p>
引用
收藏
页数:14
相关论文
共 39 条
[1]   Managing system obsolescence via multicriteria decision making [J].
Adetunji, Oluwatomi ;
Bischoff, John ;
Willy, Christopher J. .
SYSTEMS ENGINEERING, 2018, 21 (04) :307-321
[2]  
[Anonymous], 2017, PMBOK Guide
[3]  
[Anonymous], 2019, Sustainable Development Goals
[4]   A novel general risk assessment method using the soft TOPSIS approach [J].
Chang, Kuei-Hu .
JOURNAL OF INDUSTRIAL AND PRODUCTION ENGINEERING, 2015, 32 (06) :408-421
[5]   Road safety risk evaluation by means of improved entropy TOPSIS-RSR [J].
Chen, Faan ;
Wang, Jianjun ;
Deng, Yajuan .
SAFETY SCIENCE, 2015, 79 :39-54
[6]   A New Evaluation Method for Slope Stability Based on TOPSIS and MCS [J].
Chen, Wenqiang ;
Zhao, Yufei ;
Liu, Lipeng ;
Wang, Xiaogang .
ADVANCES IN CIVIL ENGINEERING, 2020, 2020
[7]   A cartography of delay risks in the Australian construction industry: impact, correlations and timing [J].
Derakhshanfar, Hossein ;
Ochoa, J. Jorge ;
Kirytopoulos, Konstantinos ;
Mayer, Wolfgang ;
Langston, Craig .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (07) :1952-1978
[8]   Construction delay risk taxonomy, associations and regional contexts A systematic review and meta-analysis [J].
Derakhshanfar, Hossein ;
Ochoa, J. Jorge ;
Kirytopoulos, Konstantinos ;
Mayer, Wolfgang ;
Tam, Vivian W. Y. .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2019, 26 (10) :2364-2388
[9]   A group risk assessment approach for the selection of pharmaceutical product shipping lanes [J].
Faghih-Roohi, Shahrzad ;
Akcay, Alp ;
Zhang, Yingqian ;
Shekarian, Ehsan ;
de Jong, Eelco .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2020, 229
[10]   Risk evaluation of tunneling projects [J].
Fouladgar, M. M. ;
Yazdani-Chamzini, A. ;
Zavadskas, E. K. .
ARCHIVES OF CIVIL AND MECHANICAL ENGINEERING, 2012, 12 (01) :1-12