Determination of early warning time window for bottleneck resource buffer

被引:6
作者
Zhang, Junguang [1 ]
Wan, Dan [1 ]
机构
[1] Univ Sci & Technol Beijing, Sch Econ & Management, Beijing 100083, Peoples R China
基金
中国国家自然科学基金;
关键词
Critical chain; Theory of constraints; Bottleneck resource; Resource buffer; Time window; ACTIVITY SENSITIVITY; PROJECT; UNCERTAINTY;
D O I
10.1007/s10479-021-03960-1
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
As an advanced warning system, resource buffer can notify the use of resources and provide added protection to critical chain activities. However, most of the existing studies in the literature focus on locating actual time buffers at various locations. In this study, we locate bottleneck resource buffers along the critical chain and determines optimal time windows for the first time. Drawing on the theory of constraints, we take into account factors such as bottleneck resource sensitivity, the idle cost, the start time flexibility and the work flow on the critical chain, and develop a quantitative model for the optimal time window determination of resource buffer. The proposed method is tested and compared with the currently widely adopted buffer management method. Results of the computational experiment of the proposed method demonstrates its relative dominance over the predominant buffer management approach in terms of overall completion time, project cost, the probability of delay and the average buffer consumption ratio.
引用
收藏
页码:289 / 305
页数:17
相关论文
共 51 条
[1]  
Ashtiani B, 2007, IN C IND ENG ENG MAN, P1037
[2]   Predetermined intervals for start times of activities in the stochastic project scheduling problem [J].
Bendavid, Illana ;
Golany, Boaz .
ANNALS OF OPERATIONS RESEARCH, 2011, 186 (01) :429-442
[3]   Buffer sizing approach with dependence assumption between activities in critical chain scheduling [J].
Bie, Li ;
Cui, Nanfang ;
Zhang, Xiaoming .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2012, 50 (24) :7343-7356
[4]   Project management and scheduling PREFACE [J].
Caramia, Massimiliano .
ANNALS OF OPERATIONS RESEARCH, 2020, 285 (1-2) :1-8
[5]  
Ching-Jong Liao, 1991, International Journal of Operations & Production Management, V11, P72, DOI 10.1108/EUM0000000001287
[6]   Resource-constrained project management using enhanced theory of constraint [J].
Wei, Chiu-Chi ;
Liu, Ping-Hung ;
Tsai, Ying-Chin .
International Journal of Project Management, 2002, 20 (07) :561-567
[7]  
Chu Chun-chao, 2008, Computer Integrated Manufacturing Systems, V14, P1029
[8]  
Craft R.C., 2002, MANAGE DECIS, V40, P729, DOI [10.1108/00251740210437699, DOI 10.1108/00251740210437699]
[9]   A new approach for quantitative risk analysis [J].
Creemers, Stefan ;
Demeulemeester, Erik ;
Van de Vonder, Stijn .
ANNALS OF OPERATIONS RESEARCH, 2014, 213 (01) :27-65
[10]  
Ghaffari M., 2015, SURVEYS OPERATIONS R, V20, P43, DOI [10.1016/j.sorms.2015.10.001, DOI 10.1016/J.SORMS.2015.10.001]