Opposition multiple objective symbiotic organisms search (OMOSOS) for time, cost, quality and work continuity tradeoff in repetitive projects

被引:50
作者
Duc-Hoc Tran [1 ,2 ]
Long Luong-Duc [1 ]
Minh-Tin Duong [1 ]
Trong-Nhan Le [1 ]
Anh-Duc Pham [2 ]
机构
[1] Ho Chi Minh City Univ Technol, Dept Construct Engn & Management, 268 Ly Thuong Kiet St,Dist 10, Ho Chi Minh City, Vietnam
[2] Univ Sci & Technol, Fac Project Management, 54 Nguyen Luong Bang Rd, Danang, Vietnam
关键词
Symbiotic organisms search; Multi-objective analysis; Resource tradeoff; Schedules; Repetitive; PARTICLE SWARM OPTIMIZATION; DIFFERENTIAL EVOLUTION ALGORITHM; ARTIFICIAL BEE COLONY; CONSTRUCTION PROJECTS; GENETIC ALGORITHM; MULTIOBJECTIVE OPTIMIZATION; LINEAR PROJECTS; OFF ANALYSIS; DISCRETE; MODEL;
D O I
10.1016/j.jcde.2017.11.008
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Construction managers often face with projects containing multiple units wherein activities repeat from unit to unit. Therefore effective resource management is crucial in terms of project duration, cost and quality. Accordingly, researchers have developed several models to aid planners in developing practical and near-optimal schedules for repetitive projects. Despite their undeniable benefits, such models lack the ability of pure simultaneous optimization because existing methodologies optimize the schedule with respect to a single factor, to achieve minimum duration, total cost, resource work breaks or various combinations, respectively. This study introduces a novel approach called "opposition multiple objective symbiotic organisms search" (OMOSOS) for scheduling repetitive projects. The proposed algorithm used an opposition-based learning technique for population initialization and for generation jumping. Further, this study integrated a scheduling module (M1) to determine all project objectives including time, cost, quality and interruption. The proposed algorithm was implemented on two application examples in order to demonstrate its capabilities in optimizing the scheduling of repetitive construction projects. The results indicate that the OMOSOS approach is a powerful optimization technique and can assist project managers in selecting appropriate plan for project. (C) 2017 Society for Computational Design and Engineering. Publishing Services by Elsevier.
引用
收藏
页码:160 / 172
页数:13
相关论文
共 76 条
[31]   An Innovative Time-Cost-Quality Tradeoff Modeling of Building Construction Project Based on Resource Allocation [J].
Hu, Wenfa ;
He, Xinhua .
SCIENTIFIC WORLD JOURNAL, 2014,
[32]   System development for non-unit based repetitive project scheduling [J].
Huang, R ;
Sun, KS .
AUTOMATION IN CONSTRUCTION, 2005, 14 (05) :650-665
[33]   Non-unit-based planning and scheduling of repetitive construction projects [J].
Huang, Rong-Yau ;
Sun, Kuo-Shun .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2006, 132 (06) :585-597
[34]   Optimal planning and scheduling for repetitive construction projects [J].
Hyari, K ;
El-Rayes, K .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2006, 22 (01) :11-19
[35]   Automated trade-off between time and cost in planning repetitive construction projects [J].
Hyari, Khalied Hesham ;
El-Rayes, Khaled ;
El-Mashaleh, Mohammad .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2009, 27 (08) :749-761
[36]  
Ipsilandis P. G., 2006, INT J, V6, P255, DOI DOI 10.1007/BF02941255
[37]   Multiobjective linear programming model for scheduling linear repetitive projects [J].
Ipsilandis, Pandelis G. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2007, 133 (06) :417-424
[38]   Optimizing the utilization of multiple labor shifts in construction projects [J].
Jun, Dho Heon ;
El-Rayes, Khaled .
AUTOMATION IN CONSTRUCTION, 2010, 19 (02) :109-119
[39]   Optimal repetitive scheduling model with shareable resource constraint [J].
Leu, SS ;
Hwang, ST .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (04) :270-280
[40]   Metaheuristics for project and construction management - A state-of-the-art review [J].
Liao, T. Warren ;
Egbelu, P. J. ;
Sarker, B. R. ;
Leu, S. S. .
AUTOMATION IN CONSTRUCTION, 2011, 20 (05) :491-505