New heuristics for total tardiness minimization in a flexible flowshop

被引:16
作者
Mainieri, Guilherme B. [1 ]
Ronconi, Debora P. [1 ]
机构
[1] Univ Sao Paulo, Dept Engn Prod, Escola Politecn, BR-05508070 Sao Paulo, Brazil
基金
巴西圣保罗研究基金会;
关键词
Scheduling; Heuristics; Flexible flowshop; Tardiness; MINIMIZING TOTAL TARDINESS; MULTIPLE PROCESSORS; SCHEDULING PROBLEM; MACHINE; SHOP; SYSTEM; RULE;
D O I
10.1007/s11590-012-0448-x
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper analyses the total tardiness minimization in a flowshop with multiple processors at each stage. While there is considerable research to minimize the makespan, very little work is reported on minimizing the total tardiness for this problem. This research focuses on heuristic methods that consider this environment as a series of parallel machine problems. New dispatching rules are introduced. One of the proposed rules is able to deal with jobs that will come afterwards and not only the available jobs at the decision time. Dispatching rules are also associated with classical (forward and backward) and new list scheduling algorithms. A special scheduling algorithm able to deal with idle times is proposed. Computational experiments in a set of 4,320 literature instances show that the developed heuristics are competitive and outperforms their classical counterparts.
引用
收藏
页码:665 / 684
页数:20
相关论文
共 28 条
[1]  
[Anonymous], 2002, Handbook of Applied Optimization
[2]  
Baker K.R., 1982, Journal of Operations Management, V3, P37, DOI [DOI 10.1016/0272-6963(82)90020-1, 10.1016/0272-6963, DOI 10.1016/0272-6963]
[3]   A comparative analysis of due date based job sequencing rules in a flow shop with multiple processors [J].
Brah, SA .
PRODUCTION PLANNING & CONTROL, 1996, 7 (04) :362-373
[4]   SOME NEW EFFICIENT METHODS TO SOLVE THE N/1/RI/SIGMA-TI SCHEDULING PROBLEM [J].
CHU, C ;
PORTMANN, MC .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1992, 58 (03) :404-413
[5]  
DAVIS JS, 1993, NAV RES LOG, V40, P85, DOI 10.1002/1520-6750(199302)40:1<85::AID-NAV3220400106>3.0.CO
[6]  
2-C
[7]   MINIMIZING TOTAL TARDINESS ON ONE MACHINE IS NP-HARD [J].
DU, JZ ;
LEUNG, JYT .
MATHEMATICS OF OPERATIONS RESEARCH, 1990, 15 (03) :483-495
[8]   A computational study of heuristics for two-stage flexible flowshops [J].
Guinet, A ;
Solomon, MM ;
Kedia, PK ;
Dussauchoy, A .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1996, 34 (05) :1399-1415
[9]  
Jin ZH, 2002, PROD OPER MANAG, V11, P216, DOI 10.1111/j.1937-5956.2002.tb00492.x
[10]   A weighted modified due date rule for sequencing to minimize weighted tardiness [J].
Kanet, JJ ;
Li, XM .
JOURNAL OF SCHEDULING, 2004, 7 (04) :261-276