Owner and contractor solution strategies for industrial commissioning

被引:6
作者
Mock, Brant [1 ]
O'Connor, James T. [1 ]
机构
[1] Univ Texas Austin, Dept Civil Environm & Architectural Engn, Austin, TX 78712 USA
来源
CONSTRUCTION INNOVATION-ENGLAND | 2019年 / 19卷 / 02期
关键词
Commissioning; Startup; Industrial construction; PICK chart; CONSTRUCTION; MANAGEMENT; PROJECTS;
D O I
10.1108/CI-09-2018-0079
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Purpose The purpose of this study is to discover which solution strategies to common industrial commissioning and startup (CSU) problems (Hot Spots) owner and contractor organizations identify as most effective and to identify which strategies are identified by one or both organization types. Design/methodology/approach Ratings for the relative value provided by strategies, and the effort required to implement strategies were solicited from CSU industry experts employed by owner or contractor organizations via a survey. Quantitative modelling using the Possible, Implement, Challenge, Kill (PICK) chart method distinguished high-value, low-effort strategies from other strategies. Findings Owners and contractors identify distinct sets of CSU solution strategies as high value and low effort, with some overlap. Of 178 total strategies, 40 (22.5 per cent) were identified by owners and 34 (19.1 per cent) by contractors, with 19 (10.7 per cent) of those strategies in common. Strategies with the greatest differences in opinions between owners and contractors are also identified. Originality/value Differences in owner and contractor perspectives and opinions have been noted in other aspects of the project lifecycle but never for CSU solution strategies. Use of the strategies identified will support more effective CSU execution.
引用
收藏
页码:256 / 279
页数:24
相关论文
共 59 条
[1]  
Abdi H., 2012, ENCY RES DESIGN, P574
[2]  
Akintoye A., 2000, Construction Management Economics, V18, P77, DOI DOI 10.1080/014461900370979
[3]  
Al Ahbabi Mubarak, 2015, Construction Innovation, V15, P402, DOI 10.1108/CI-04-2015-0023
[4]  
Albers M.J., 2017, INTRO QUANTITATIVE D, P87
[5]   Pre-commissioning, commissioning and start-up of industrial plants and machineries [J].
Almasi, A. .
AUSTRALIAN JOURNAL OF MECHANICAL ENGINEERING, 2014, 12 (02) :257-263
[6]  
[Anonymous], 2012, J BUSINESS CHEM
[7]  
[Anonymous], 2001, NEW STEEL
[8]  
Badiru A.B., 2013, Journal of Enterprise Transformation, DOI [DOI 10.1080/19488289.2013.784221, 10.1080/19488289.2013.784221]
[9]   Late Deliverable Risk Catalog: Evaluating the Impacts and Risks of Late Deliverables to Construction Sites [J].
Barry, William ;
Leite, Fernanda ;
O'Brien, William J. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (04)
[10]  
Biloshapka Vladyslav, 2016, Strategy & Leadership, V44, P41, DOI 10.1108/SL-04-2016-0026