Optimal control strategies for single-machine family scheduling with sequence-dependent batch setup and controllable processing times

被引:14
作者
Giglio, Davide [1 ]
机构
[1] Univ Genoa, Dept Informat Bioengn Robot & Syst Engn, I-16145 Genoa, Italy
关键词
Optimal control; Family scheduling problems; Sequence-dependent setup; Controllable processing times; Dynamic programming; MANUFACTURING SYSTEMS; MAXIMUM LATENESS; TOTAL TARDINESS; RELEASE TIMES; EARLINESS; JOBS; COMPLEXITY; ALGORITHM; DATES;
D O I
10.1007/s10951-015-0440-2
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The problem of scheduling jobs on an unreliable single machine is considered in this paper. The scheduling problem is characterized by the following features: jobs are grouped into classes of equivalent jobs; the generalized due date model is adopted for each class of jobs; it is possible to reduce the processing time of a job, at the price of the payment of an extra cost; a costly setup is required when switching between jobs of different classes. The scheduling problem is solved from a perspective which is different from the traditional determination of an optimal sequence of jobs; in fact, the objective of the paper is to determine optimal control strategies (functions of the system state) which allow generating the optimal decisions during the evolution of the system, taking into account the actual system state. In this way, optimal decisions can be promptly taken also in the presence of perturbations which affect the single machine (such as breakdowns and slowdowns). To this aim, a specific optimal control problem is stated and solved in the paper.
引用
收藏
页码:525 / 543
页数:19
相关论文
共 70 条
[1]  
Aicardi Michele, 2007, Proceedings of the European Control Conference 2007 (ECC), P3963
[2]   Optima strategies for multiclass job scheduling on a single machine with controllable processing times [J].
Aicardi, Michele ;
Giglio, Davide ;
Minciardi, Riccardo .
IEEE TRANSACTIONS ON AUTOMATIC CONTROL, 2008, 53 (02) :479-495
[3]   OPTIMAL-CONTROL OF PRODUCTION-RATE IN A FAILURE PRONE MANUFACTURING SYSTEM [J].
AKELLA, R ;
KUMAR, PR .
IEEE TRANSACTIONS ON AUTOMATIC CONTROL, 1986, 31 (02) :116-126
[4]   Single CNC machine scheduling with controllable processing times to minimize total weighted tardiness [J].
Akturk, M. Selim ;
Ilhan, Taylan .
COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (04) :771-781
[5]   A review of scheduling research involving setup considerations [J].
Allahverdi, A ;
Gupta, JND ;
Aldowaisan, T .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1999, 27 (02) :219-239
[6]   A survey of scheduling problems with setup times or costs [J].
Allahverdi, Ali ;
Ng, C. T. ;
Cheng, T. C. E. ;
Kovalyov, Mikhail Y. .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 187 (03) :985-1032
[7]   Executing production schedules in the face of uncertainties: A review and some future directions [J].
Aytug, H ;
Lawley, MA ;
McKay, K ;
Mohan, S ;
Uzsoy, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 161 (01) :86-110
[8]   Single-machine scheduling with advanced process control constraints [J].
Cai, Yiwei ;
Kutanoglu, Erhan ;
Hasenbein, John ;
Qin, Joe .
JOURNAL OF SCHEDULING, 2012, 15 (02) :165-179
[9]   Bicriterion single machine scheduling with resource dependent processing times [J].
Cheng, TCE ;
Janiak, A ;
Kovalyov, MY .
SIAM JOURNAL ON OPTIMIZATION, 1998, 8 (02) :617-630
[10]   SINGLE-MACHINE BATCH SCHEDULING WITH DEADLINES AND RESOURCE DEPENDENT PROCESSING TIMES [J].
CHENG, TCE ;
KOVALYOV, MY .
OPERATIONS RESEARCH LETTERS, 1995, 17 (05) :243-249