Minimizing total weighted late work in the resource-constrained project scheduling problem

被引:16
作者
Ranjbar, Mohammad [1 ]
Hosseinabadi, Saeed [1 ]
Abasian, Foroogh [1 ]
机构
[1] Ferdowsi Univ Mashhad, Dept Ind Engn, Fac Engn, Mashhad, Iran
关键词
Resource-constrained project scheduling; Late work; Branch-and-bound; JOB-SHOP; ALGORITHM;
D O I
10.1016/j.apm.2013.05.013
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper deals with resource-constrained project scheduling problem under the weighted late work criterion. Late work objective functions estimate the quality of a schedule based on durations of late parts of activities, not taking into account the amount of delay for fully late activities. It is assume that a project contains activities interrelated by finish-to-start type precedence relations with time lag of zero, which require one or more constrained renewable resources. The objective is to schedule each activity such that the total weighted late work is minimized. The problem has been formulated using a linear integer programming model and solved by the CPLEX. Also, a set of priority rules have been designed to quickly generate a set of initial solutions. In order to solve the problem optimally, a depth-first branch-and-bound algorithm is applied based on idea of minimal delaying alternatives. The branching order of nodes that belong to the same level of the search tree is determined on the basis of the developed priority rules. This results in generation six different versions of the branch-and-bound algorithm. Computational results on randomly generated problem sets are provided to analyze the efficiency of the priority rules and the branch-and-bound algorithm. (C) 2013 Elsevier Inc. All rights reserved.
引用
收藏
页码:9776 / 9785
页数:10
相关论文
共 27 条
  • [1] A Neurogenetic approach for the resource-constrained project scheduling problem
    Agarwal, Anurag
    Colak, Selcuk
    Erenguc, Selcuk
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2011, 38 (01) : 44 - 50
  • [2] The two-machine flow-shop problem with weighted late work criterion and common due date
    Blazewicz, J
    Pesch, E
    Sterna, M
    Werner, F
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 165 (02) : 408 - 415
  • [3] Open shop scheduling problems with late work criteria
    Blazewicz, J
    Pesch, E
    Sterna, M
    Werner, F
    [J]. DISCRETE APPLIED MATHEMATICS, 2004, 134 (1-3) : 1 - 24
  • [4] BLAZEWICZ J, 1984, TSI-TECH SCI INF, V3, P415
  • [5] A note on the two machine job shop with the weighted late work criterion
    Blazewicz, Jacek
    Pesch, Erwin
    Sterna, Malgorzata
    Werner, Frank
    [J]. JOURNAL OF SCHEDULING, 2007, 10 (02) : 87 - 95
  • [6] RanGen: A random network generator for activity-on-the-node networks
    Demeulemeester, E
    Vanhoucke, M
    Herroelen, W
    [J]. JOURNAL OF SCHEDULING, 2003, 6 (01) : 17 - 38
  • [7] A BRANCH-AND-BOUND PROCEDURE FOR THE MULTIPLE RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM
    DEMEULEMEESTER, E
    HERROELEN, W
    [J]. MANAGEMENT SCIENCE, 1992, 38 (12) : 1803 - 1818
  • [8] Demeulemeester E., 2002, Project Scheduling: A Research Handbook
  • [9] An effective shuffled frog-leaping algorithm for resource-constrained project scheduling problem
    Fang, Chen
    Wang, Ling
    [J]. COMPUTERS & OPERATIONS RESEARCH, 2012, 39 (05) : 890 - 901
  • [10] Hariri A. M. A., 1995, ORSA Journal on Computing, V7, P232, DOI 10.1287/ijoc.7.2.232