Investigating cost overruns and delay in urban construction projects in Iran

被引:35
作者
Heravi, Gholamreza [1 ]
Mohammadian, Meghdad [2 ]
机构
[1] Univ Tehran, Coll Engn, Sch Civil Engn, Tehran, Iran
[2] Univ Tehran, Sch Civil Engn, Coll Engn, Tehran, Iran
关键词
Urban construction project; delay; cost overruns; developing countries; Iran; TIME; PERFORMANCE; INDUSTRY;
D O I
10.1080/15623599.2019.1601394
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Urban construction, as one of the most important sectors of construction industry in Iran, commonly faces significant cost overruns and delay. The main objective of this study is to evaluate how small, medium and large urban construction projects perform in terms of cost and time. Moreover, different types (road or building) and nature (new or renovation) of construction projects are considered in this research. This study looks at the urban construction projects in Karaj, the capital of Alborz Province, Iran. In this study, 72 urban construction projects are surveyed by reviewing their documents and their real performance. To analyze the collected data, the statistical analyses including class range analysis, independent-sample T-test and correlation analysis are used. This study shows that large urban construction projects are faced higher cost overruns and delay. Moreover, the time- and cost-performance of the new-build projects in overall is better than renovation projects. Furthermore, the cost-performance of urban road projects is better than building projects. The findings offer descriptive statistical cost and time performance information to support realistic time and cost estimation in urban construction projects.
引用
收藏
页码:958 / 968
页数:11
相关论文
共 60 条
[1]   Factors affecting contractors' risk of cost overburden [J].
Akinci, B ;
Fischer, M .
JOURNAL OF MANAGEMENT IN ENGINEERING, 1998, 14 (01) :67-76
[2]  
Alinaitwe H, 2013, J CONSTR DEV CTRIES, V18, P33
[3]  
[Anonymous], 2017, A Guide to the SCRUM BODY OF KNOWLEDGE (SBOK TM GUIDE) Third Edition A Comprehensive Guide to Deliver Projects using Scrum Includes two chapters about Scaling Scrum for Large Projects and the Enterprise
[4]  
[Anonymous], 2016, Journal of Construction in Developing Countries, V21, P51, DOI [DOI 10.21315/JCDC2016.21.1.4, 10.21315/jcdc2016.21.1]
[5]  
[Anonymous], 2014, INT C IND ENG OP MAN
[6]   Factors influencing accuracy of construction project cost estimates in Pakistan: Perception and reality [J].
Arif, Farrukh ;
Lodi, Sarosh H. ;
Azhar, Nida .
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2015, 15 (01) :59-70
[7]   Causes of delay in large construction projects [J].
Construction Engineering and Management Department, King Fahd University of Petroleum and Minerals, Box # 680, Dhahran, 31261, Saudi Arabia .
Int. J. Proj. Manage., 2006, 4 (349-357) :349-357
[8]   Ranking of delay factors in construction projects after Egyptian revolution [J].
Aziz, Remon Fayek .
ALEXANDRIA ENGINEERING JOURNAL, 2013, 52 (03) :387-406
[9]  
Baccarini D., 1996, International Journal of Project Management, V14, P201, DOI 10.1016/0263-7863(95)00093-3
[10]   Cost forecasting using RCF: a case study for planning public building projects costs in Turkey [J].
Bayram, Savas ;
Al-Jibouri, Saad .
INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2018, 18 (05) :405-417