Batch scheduling problem for a machinery factory with fixed-position layout

被引:11
作者
Lin, Rock [1 ]
Liao, Ching-Jong [1 ]
机构
[1] Natl Taiwan Univ Sci & Technol, Dept Ind Management, Taipei 106, Taiwan
关键词
fixed-position layout; job dividing; batch processing; family batch setup time; removal time; mixed integer programming; 2-MACHINE FLOW-SHOP; TOTAL COMPLETION-TIME; PROCESSING MACHINE; GENETIC ALGORITHMS; 2-STAGE FLOWSHOP; LIMITED BUFFER; SETUP TIMES; JOBS; TARDINESS;
D O I
10.1080/00207543.2012.693216
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We consider a batch scheduling problem for a two-stage flow shop with fixed-position layout. In the first stage, a fixed number of jobs are assembled on a batch machine with a family batch setup time and a common processing time. In the second stage, the assembled jobs are individually performed for system integration on a discrete machine. The finished job is immediately packed and shipped if the payment has been made; otherwise, it is moved to a temporary storage area, incurring additional removal time. This study develops a mixed integer programming (MIP) to solve the problem of minimising the total completion time and proposes two heuristics for large-size problems. Computational results show that the proposed methods can be applied to resolve real-world problems similar to those in this study.
引用
收藏
页码:910 / 926
页数:17
相关论文
共 40 条
[1]  
Agnetis A, 1998, NAV RES LOG, V45, P141, DOI 10.1002/(SICI)1520-6750(199803)45:2<141::AID-NAV2>3.0.CO
[2]  
2-8
[3]   BATCHING AND SCHEDULING JOBS ON BATCH AND DISCRETE PROCESSORS [J].
AHMADI, JH ;
AHMADI, RH ;
DASU, S ;
TANG, CS .
OPERATIONS RESEARCH, 1992, 40 (04) :750-763
[4]   A review of scheduling research involving setup considerations [J].
Allahverdi, A ;
Gupta, JND ;
Aldowaisan, T .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1999, 27 (02) :219-239
[5]   A survey of scheduling problems with setup times or costs [J].
Allahverdi, Ali ;
Ng, C. T. ;
Cheng, T. C. E. ;
Kovalyov, Mikhail Y. .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 187 (03) :985-1032
[6]  
[Anonymous], INTRO OPERATIONS RES
[7]   Minimizing maximum lateness with job families [J].
Baker, KR ;
Magazine, MJ .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2000, 127 (01) :126-139
[8]   SCHEDULING GROUPS OF JOBS IN THE 2-MACHINE FLOW-SHOP [J].
BAKER, KR .
MATHEMATICAL AND COMPUTER MODELLING, 1990, 13 (03) :29-36
[9]  
Brucker P., 1998, Journal of Scheduling, V1, P31, DOI 10.1002/(SICI)1099-1425(199806)1:1<31::AID-JOS4>3.0.CO
[10]  
2-R