Analysis of grounding status of substation secondary system and improvement measures
被引:0
作者:
He Xuedong
论文数: 0引用数: 0
h-index: 0
机构:
State Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
NR Elect Co Ltd, Nanjing 211106, Jiangsu, Peoples R ChinaState Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
He Xuedong
[1
,2
]
Yan Wei
论文数: 0引用数: 0
h-index: 0
机构:
State Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
NR Elect Co Ltd, Nanjing 211106, Jiangsu, Peoples R ChinaState Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
Yan Wei
[1
,2
]
Li Xinghua
论文数: 0引用数: 0
h-index: 0
机构:
State Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
NR Elect Co Ltd, Nanjing 211106, Jiangsu, Peoples R ChinaState Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
Li Xinghua
[1
,2
]
Song Xiangping
论文数: 0引用数: 0
h-index: 0
机构:
State Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
NR Elect Co Ltd, Nanjing 211106, Jiangsu, Peoples R ChinaState Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
Song Xiangping
[1
,2
]
Huang Xuyin
论文数: 0引用数: 0
h-index: 0
机构:
Wuhan Puxin Elect Design Co, Wuhan 430000, Hubei, Peoples R ChinaState Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
Huang Xuyin
[3
]
机构:
[1] State Grid Elect Power Res Inst Co Ltd, NARI Grp Corp, Nanjing 211106, Jiangsu, Peoples R China
[2] NR Elect Co Ltd, Nanjing 211106, Jiangsu, Peoples R China
[3] Wuhan Puxin Elect Design Co, Wuhan 430000, Hubei, Peoples R China
来源:
2018 CHINA INTERNATIONAL CONFERENCE ON ELECTRICITY DISTRIBUTION (CICED)
|
2018年
In this paper , the present situation of secondary system grounding in substation is comprehensively analyzed, some improvement measures are put forward, such as perfecting setting of secondary grounding grid, improving anti-interference ability of secondary equipment, canceling insulated copper bar in cabinet, making clear grounding mode of cable shielding layer, increasing protection of the weak electrical signal cable, have solved the problem of grounding frequently occurring in engineering.
引用
收藏
页码:1479 / 1483
页数:5
相关论文
共 1 条
[1]
CIGRE Working Group, 1997, GUID EMC POW PLANTS