Comparing Project Performance of Design-Build and Design-Bid-Build Methods for Large-sized Public Apartment Housing Projects in Korea

被引:29
|
作者
Park, Hye-Sung [1 ]
Lee, Donghoon [1 ]
Kim, Sunkuk [1 ]
Kim, Jin-Lee [1 ,2 ]
机构
[1] Kyung Hee Univ, Dept Architectural Engn, Gyeonggi Do, South Korea
[2] Calif State Univ Long Beach, Dept Civil Engn & Construct Engn Management, Long Beach, CA 90840 USA
关键词
project delivery; design-build; design-bid-build; construction management; project performance;
D O I
10.3130/jaabe.14.323
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The project delivery method has a great impact on project performance and construction quality. The numerous studies on the project performance of the two project delivery methods, design-bid-build (DBB) and design-build (DB), have found differing results depending on the project locations, the project types, and the project sizes. Since no previous studies have been conducted with regard to large-sized apartment housing projects, this paper presents the comparative analysis results for the project performance of the DB and DBB methods, focusing on the large-sized public apartment housing projects built in Korea. The project performances considered include cost, cost growth, construction duration, construction duration growth, and quality performance. The cost and schedule performance analysis results show that the cost growth of the DB method is about 5% lower than that of the DBB method and the construction duration is shortened by twelve days per floor. The quality performance analysis results demonstrate that the satisfaction with the DB method is higher in terms of the construction quality and efficiency of the DB method. This paper contributes to the growing body of research into the efficiency of project delivery methods, expanding the body of knowledge for large-sized public apartment housing projects.
引用
收藏
页码:323 / 330
页数:8
相关论文
共 41 条
  • [31] Contractual Risks of Building Information Modeling: Toward a Standardized Legal Framework for Design-Bid-Build Projects
    Arshad, Muhammad Farhan
    Thaheem, Muhammad Jamaluddin
    Nasir, Abdur Rehman
    Malik, Muhammad Sohail Anwar
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2019, 145 (04)
  • [32] Critical success factors for implementing design-build: analysing Malaysian public projects
    Lee, Zheng Ping
    Rahman, Rahimi A.
    Doh, Shu Ing
    JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2022, 20 (05) : 1041 - 1056
  • [33] Enhancing design-bid-build project delivery: A comprehensive review and framework for contractor selection and project optimisation in the construction industry
    Almuhannadi, Mohammed Ali
    Ghareeb, Ahmed Salem
    ORGANIZATION TECHNOLOGY AND MANAGEMENT IN CONSTRUCTION, 2024, 16 (01): : 63 - 80
  • [34] Study of the Relationship between Procurement Duration and Project Performance in Design-Build Projects: Comparison between Water/Wastewater and Transportation Sectors
    Bogus, Susan M.
    Migliaccio, Giovanni C.
    Jin, Ruoyu
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2013, 29 (04) : 382 - 391
  • [35] A SYNTHESIS OF BEST-VALUE PROCUREMENT PRACTICES FOR SUSTAINABLE DESIGN-BUILD PROJECTS IN THE PUBLIC SECTOR
    Molenaar, Keith R.
    Sobin, Nathaniel
    Antillon, Eric I.
    JOURNAL OF GREEN BUILDING, 2010, 5 (04): : 148 - 157
  • [36] Change Orders and Schedule Performance of Design-Build Infrastructure Projects: Comparison between Highway and Water and Wastewater Projects
    Fathi, Medya
    Shrestha, Pramen P.
    Shakya, Binita
    JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2020, 12 (01)
  • [37] Impediments in Using Design-Build or Construction Management-at-Risk Delivery Methods for Water and Wastewater Projects
    Shrestha, Pramen P.
    Batista, Jacimaria
    Maharjan, Ruiko
    CONSTRUCTION RESEARCH CONGRESS 2016: OLD AND NEW CONSTRUCTION TECHNOLOGIES CONVERGE IN HISTORIC SAN JUAN, 2016, : 380 - 387
  • [38] Legal and Contractual Issues in Lump-Sum Design-Build Implementation on Large-Scale Airport Projects
    Gad, Ghada M.
    Davis, Brandon
    Shrestha, Pramen P.
    Fathi, Medya
    JOURNAL OF LEGAL AFFAIRS AND DISPUTE RESOLUTION IN ENGINEERING AND CONSTRUCTION, 2020, 12 (01)
  • [39] Long-Term Performance Benefits of the Design-Build Delivery Method Applied to Road Pavement Projects in the US
    Cho, Namho
    El Asmar, Mounir
    Underwood, Shane
    Kamarianakis, Yiannis
    KSCE JOURNAL OF CIVIL ENGINEERING, 2020, 24 (04) : 1049 - 1059
  • [40] Designer-led Design/Build - Alternative project delivery method for facade evaluation and repair projects - Case study on an 11 story apartment building
    VanOcker, DA
    BUILDING FACADE MAINTENANCE, REPAIR, AND INSPECTION, 2004, 1444 : 274 - 290