Causes-Effects Relationship of Construction Project Delays in Ghana: Focusing on Local Government Projects

被引:3
|
作者
Ametepey, Simon Ofori [1 ]
Gyadu-Asiedu, William [1 ]
Assah-Kissiedu, Millicent [1 ]
机构
[1] Koforidua Tech Univ, Fac Built & Nat Environm, Koforidua, Ghana
关键词
Causes; Construction; Effects; Ghana; Local government; Project delay;
D O I
10.1007/978-3-319-60450-3_9
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Project delays in the construction industry are a worldwide phenomenon and local government construction projects in Ghana are not an exception. The paper presents the results of a survey conducted to identify and assess the severity of the causes of local government construction project delays and their effect in Ghana. In previous research, the causes and the effects of project delays has been studied without considering the possible relationship that exist between them. This study takes a combined approach and also sought to analyze the relationship between specific causes on specific effects. The results of the study revealed the main causes of schedule delays in local government construction projects as: delay in progress payments; variation orders during construction; difficulties in financing projects by contractors; delay in material delivery; and unforeseen site conditions. The study further identified the effects of delay as: time overrun; cost overrun; delay by contractor in repayment of loans; disputes; and poor quality work due to speeding up of work. The study also established an empirical correlation between each cause and effect. The study revealed that bulk of the effects of delay of local government construction projects is triggered by client-related and contractor-related causes.
引用
收藏
页码:84 / 95
页数:12
相关论文
共 50 条
  • [1] Delays in Building Construction Projects in Ghana
    Fugar, Frank D. K.
    Agyakwah-Baah, Adwoa B.
    CONSTRUCTION ECONOMICS AND BUILDING, 2010, 10 (1-2):
  • [2] Causes of government construction projects failure in an emerging economy: Evidence from Ghana
    Damoah, Isaac Sakyi
    Kumi, Desmond Kwadjo
    INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2018, 11 (03) : 558 - 582
  • [3] CAUSES OF DELAYS IN IRANIAN CONSTRUCTION PROJECTS
    Khoshgoftar, Mohammad
    Abu Bakar, Abu Hassan
    Osman, Omar
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2010, 10 (02) : 53 - 69
  • [4] Delays in construction projects - Causes and impacts
    Arantes, Amlcar
    da Silva, Pedro Fernandez
    Ferreira, Luis Miguel D. F.
    2015 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM), 2015, : 1105 - 1110
  • [5] CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY
    Kazaz, Aynur
    Ulubeyli, Serdar
    Tuncbilekli, Nihan Avcioglu
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2012, 18 (03) : 426 - 435
  • [6] Construction projects: interactions of the causes of delays
    Purushothaman, Mahesh Babu
    San Pedro, Leo Neil Resurreccion
    GhaffarianHoseini, Ali
    SMART AND SUSTAINABLE BUILT ENVIRONMENT, 2024,
  • [7] Analyzing Delays of Road Construction Projects in Cambodia: Causes and Effects
    San Santoso, Djoen
    Soeng, Sothy
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2016, 32 (06)
  • [8] Causes of government construction projects' abandonment
    Damoah, Isaac Sakyi
    Ayakwa, Anthony
    Kumi, Desmond Kwadjo
    JOURNAL OF PROJECT MANAGEMENT, 2021, 6 (04) : 179 - 190
  • [9] Causes of Construction Projects Delays: A qualitative analysis
    Rudeli, N.
    Viles, E.
    Gonzalez, J.
    Santilli, A.
    MEMORIA INVESTIGACIONES EN INGENIERIA, 2018, (16): : 71 - 84
  • [10] Causes of delays on construction projects: a comprehensive list
    Durdyev, Serdar
    Hosseini, M. Reza
    INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2019, 13 (01) : 20 - 46