Time Overrun Causes in construction Projects in Saudi Arabia: Consultants' Perspective

被引:0
|
作者
Mahamid, Ibrahim [1 ]
Alhomaydan, Abdullah [1 ]
机构
[1] Hail Univ, Dept Civil Engn, Hail, Saudi Arabia
来源
2013 3RD INTERNATIONAL CONFERENCE ON APPLIED SOCIAL SCIENCE (ICASS 2013), VOL 1 | 2013年
关键词
Time overrun; Delay; Construction; Saudi Arabia;
D O I
暂无
中图分类号
C [社会科学总论];
学科分类号
03 ; 0303 ;
摘要
This study is conducted to identify the main factors affecting time overrun in construction projects in Saudi Arabia from consultants' perspective. The importance index of each factor is calculated. 35 factors were identified through literature review. The identified causes are combined into five groups. A field survey included 23 consultants from the northern part of Saudi Arabia was performed. The findings reveal that the top five affecting factors from consultants' perspective are: improper planning, inflationary pressure, fluctuation of material prices, poor labor productivity, and payments delay.
引用
收藏
页码:114 / 119
页数:6
相关论文
共 50 条
  • [1] Cost Overrun Causes in Road Construction Projects: "Consultants' Perspective"
    Mahamid, Ibrahim
    Bruland, Amund
    CONSTRUCTION AND PROJECT MANAGEMENT, ICCPM 2011, 2011, 15 : 6 - 10
  • [2] Severity of Time Overrun Causes in Road Construction Projects: Contractors' Perspective
    Mahamid, Ibrahim
    Bruland, Amund
    PROCEEDINGS OF 2011 INTERNATIONAL CONFERENCE ON CONSTRUCTION AND REAL ESTATE MANAGEMENT, VOLS 1 AND 2, 2011, : 191 - 194
  • [3] Causes of Time Overrun in Construction of Building Projects in Pakistan
    Soomro, Faheem Ahmed
    Memon, Muhammed Jaffar
    Chandio, Abdul Fattah
    Sohu, Samiullah
    Soomro, Rizwanullah
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2019, 9 (01) : 3762 - 3764
  • [4] Significant causes of claims and disputes in construction projects in Saudi Arabia
    Assaf, Sadi
    Hassanain, Mohammad A.
    Abdallah, Abdullatif
    Sayed, Ahmed M. Z.
    Alshahrani, Abdulrahman
    BUILT ENVIRONMENT PROJECT AND ASSET MANAGEMENT, 2019, 9 (05) : 597 - 615
  • [5] Causes of Construction Projects Cost Overrun in Brazil
    Franca, Alda
    Haddad, Assed
    INTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 2018, 9 (01): : 69 - 83
  • [6] Time and Cost Overrun in Construction Projects in Ecuador: Main Causes and Risk Factors
    Manzano-Alvarado, Mateo
    Montalban-Domingo, Laura
    Garcia-Segura, Tatiana
    Sanz-Benlloch, Amalia
    Pellicer, Eugenio
    CONSTRUCTION RESEARCH CONGRESS 2024: CONTRACTING, DELIVERY, SCHEDULING, ESTIMATING, ECONOMICS, AND ORGANIZATIONAL MANAGEMENT AND PLANNING IN CONSTRUCTION, 2024, : 238 - 244
  • [7] Common Risks Affecting Time Overrun in Road Construction Projects in Palestine: Contractors' Perspective
    Mahamid, Ibrahim
    CONSTRUCTION ECONOMICS AND BUILDING, 2013, 13 (02): : 45 - 53
  • [8] Assessing the Impact of Cost Overrun Causes in Transmission Lines Construction Projects
    Pham, Hai
    Luu, Truong-Van
    Kim, Soo-Yong
    Vien, Duc-Thinh
    KSCE JOURNAL OF CIVIL ENGINEERING, 2020, 24 (04) : 1029 - 1036
  • [9] Causes of material delays in capital projects in Saudi Arabia
    Shash, Ali A.
    AbuAlnaja, Fahad M.
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2023, 23 (07) : 1109 - 1117
  • [10] Assessing the Impact of Cost Overrun Causes in Transmission Lines Construction Projects
    Hai Pham
    Truong-Van Luu
    Soo-Yong Kim
    Duc-Thinh Vien
    KSCE Journal of Civil Engineering, 2020, 24 : 1029 - 1036