Probabilistic Method for Managing Common Risks in Software Project Scheduling Based on Program Evaluation Review Technique

被引:6
作者
Huynh, Quyet-Thang [1 ]
Nguyen, Ngoc-Tuan [1 ]
机构
[1] Hanoi Univ Sci & Technol, Hanoi, Vietnam
关键词
Bayesian Networks; PERT; Project Risks; Project Scheduling; Risk Factors; MODEL;
D O I
10.4018/IJITPM.2020070105
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
Project management and project scheduling are crucial to help development teams keep track of timing as well as resource allocation. In order to manage software projects, project managers need to anticipate, analyze the risk factors that may occur as well as their impacts on the progress of the project, and assess and adapt the project resource allocation. This paper concentrates on a quantitative approach for risk analysis in software project scheduling by taking advantage of Bayesian networks capacity (including related mathematical calculations) in modeling and assessing uncertainty and incorporates them in software project scheduling with program evaluation and review technique (PERT). Common risk factors in project scheduling are also examined, and a Bayesian networks model of 19 common risk factors and their causal relationships is proposed and confirmed. The research also borrows and implements categories and levels of risk from construction projects into software projects. A tool was built to experiment and validate the proposed model.
引用
收藏
页码:77 / 94
页数:18
相关论文
共 22 条
  • [1] [Anonymous], J SCI TECHNOLOGY SEC
  • [2] Chang H. K., 2017, P 34 INT S AUT ROB C, DOI [10.22260/ISARC2017/0072, DOI 10.22260/ISARC2017/0072]
  • [3] Decision Support Software for Probabilistic Risk Assessment Using Bayesian Networks
    Fenton, Norman
    Neil, Martin
    [J]. IEEE SOFTWARE, 2014, 31 (02) : 21 - 26
  • [4] Software project risk analysis using Bayesian networks with causality constraints
    Hu, Yong
    Zhang, Xiangzhou
    Ngai, E. W. T.
    Cai, Ruichu
    Liu, Mei
    [J]. DECISION SUPPORT SYSTEMS, 2013, 56 : 439 - 449
  • [5] Kaur R., 2013, INT J COMPUTER SCI E, V4, P877
  • [6] Khodakarami V., 2007, PROJ MANAG J, V38, P39, DOI [https://doi.org/10.1177/875697280703800205, DOI 10.1177/875697280703800205]
  • [7] A Probabilistic Software Risk Assessment and Estimation Model for Software Projects
    Kumar, Chandan
    Yadav, Dilip Kumar
    [J]. ELEVENTH INTERNATIONAL CONFERENCE ON COMMUNICATION NETWORKS, ICCN 2015/INDIA ELEVENTH INTERNATIONAL CONFERENCE ON DATA MINING AND WAREHOUSING, ICDMW 2015/NDIA ELEVENTH INTERNATIONAL CONFERENCE ON IMAGE AND SIGNAL PROCESSING, ICISP 2015, 2015, 54 : 353 - 361
  • [8] Liberatore M.J., 2005, PROJ MANAG J, V36, P15
  • [9] Schedule Uncertainty Control: A Literature review
    Liu Jun-yan
    [J]. 2012 INTERNATIONAL CONFERENCE ON MEDICAL PHYSICS AND BIOMEDICAL ENGINEERING (ICMPBE2012), 2012, 33 : 1842 - 1848
  • [10] APPLICATION OF A TECHNIQUE FOR RESEARCH AND DEVELOPMENT PROGRAM-EVALUATION
    MALCOLM, DG
    ROSEBOOM, JH
    CLARK, CE
    FAZAR, W
    [J]. OPERATIONS RESEARCH, 1959, 7 (05) : 646 - 669