1976 Montreal Olympics: Case Study of Project Management Failure

被引:6
|
作者
Patel, Ashish [1 ,2 ]
Bosela, Paul A. [2 ]
Delatte, Norbert J. [2 ]
机构
[1] HWH Architects Engineers Planners Inc, Cleveland, OH 44114 USA
[2] Cleveland State Univ, Dept Civil & Environm Engn, Cleveland, OH 44115 USA
基金
美国国家科学基金会;
关键词
Project management; Construction; Precast concrete; Project scheduling;
D O I
10.1061/(ASCE)CF.1943-5509.0000332
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
A successful engineering project must include its timely and economic completion. Aproject management failure can lead to delays and cost overruns. One example of a project that greatly exceeded its projected budget is the construction of the multiple facilities for the 1976 Olympic Games in Montreal. These included the Olympic Stadium, a velodrome for bicycle events, and the Olympic Village to house the athletes. This case study reviews the circumstances of the cost increases and the design decisions and other circumstances that led to them. The difficulties were brought on by an unrealistic schedule to complete the facilities before the fixed start date of the Games, combined with an unusually cavalier attitude toward project costs, exacerbated by political tensions. Although the original cost estimate for the facilities was $120 million, the final cost was $1.5 billion, with $830 million for the main stadium alone. Part of the justification for the expense of the facilities was the hope that the facilities would be useful for future athletic events-the record on this is mixed at best. The lessons learned can be applied to other projects to better control costs. (C) 2013 American Society of Civil Engineers.
引用
收藏
页码:362 / 369
页数:8
相关论文
共 50 条
  • [1] The Transformation of Security Planning for the Olympics: The 1976 Montreal Games
    Clement, Dominique
    TERRORISM AND POLITICAL VIOLENCE, 2017, 29 (01) : 27 - 51
  • [2] PHYSIQUE OF FEMALE SWIMMERS AND DIVERS FROM THE 1976 MONTREAL OLYMPICS
    KHOSLA, T
    JAMA-JOURNAL OF THE AMERICAN MEDICAL ASSOCIATION, 1984, 252 (04): : 536 - 537
  • [3] Marketing Avery Brundage's Apoplexy: The 1976 Montreal Olympics Self-Financing Model
    Fresco, Estee
    INTERNATIONAL JOURNAL OF THE HISTORY OF SPORT, 2016, 33 (04): : 369 - 384
  • [4] Manufacturing the Image of a Country through Sport: Granma's Press Coverage of Cuba's Performance from the 1976 Montreal Olympics to the 2016 Rio Olympics
    Hasbani, Victor
    Cortinas-Rovira, Sergi
    Ramon, Xavier
    INTERNATIONAL JOURNAL OF THE HISTORY OF SPORT, 2021, 38 (04): : 368 - 391
  • [5] Learning Project Management through Case Study Project Work as Case Study
    Anushalalitha, T.
    2014 IEEE INTERNATIONAL CONFERENCE ON MOOC, INNOVATION AND TECHNOLOGY IN EDUCATION (MITE), 2014, : 193 - 197
  • [6] THE MANAGEMENT OF A COMMUNITY PROJECT - A CASE STUDY
    Louw, E. J.
    Maubane, T. J.
    BUSINESS MANAGEMENT CONFERENCE 2009, 2009, : 480 - 486
  • [7] The CeMENT project: a case study in change management
    Macfarlane, F
    Gantley, M
    Murray, E
    MEDICAL TEACHER, 2002, 24 (03) : 320 - 326
  • [8] Community management and project sustianability - Case Study
    Katakweba, M
    PEOPLE AND SYSTEMS FOR WATER, SANITATION AND HEALTH, 2001, : 283 - 286
  • [9] Comprehensive Reorganization of Project Management: A Case Study
    Apaolaza, Unai
    Lizarralde, Aitor
    PROJECT MANAGEMENT AND ENGINEERING RESEARCH, AEIPRO 2016, 2017, : 3 - 17
  • [10] Global Software Project Management: A Case Study
    Bjorndal, Petra
    Smiley, Karen
    Mohapatra, Prateeti
    SOFTWARE ENGINEERING APPROACHES FOR OFFSHORE AND OUTSOURCED DEVELOPMENT, 2010, 54 : 64 - +