Placement of protective devices in distribution system considering uncertainties in loads, temporary and permanent failure rates and repair rates

被引:30
作者
Alam, Afroz [1 ]
Alam, Mahamad Nabab [1 ]
Pant, Vinay [1 ]
Das, Biswarup [1 ]
机构
[1] Indian Inst Technol, Dept Elect Engn, Roorkee 247667, Uttar Pradesh, India
关键词
power distribution protection; electric fuses; integer programming; linear programming; circuit breakers; fuse-save fuses; fuse-blow fuses; switches; reclosers; mixed integer nonlinear programming optimisation technique; generalised objective function; three-point estimate method; load data; temporary failure rates uncertainties; fuse-save scheme; sustained interruption; fuse-blow scheme; momentary interruptions reduction; temporary failure rates; repair rates; permanent failure rates; load uncertainties; distribution system; protective devices placement; SWITCH PLACEMENT; RELIABILITY;
D O I
10.1049/iet-gtd.2017.0075
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
Distribution system reliability is directly affected by the placement of various types of protective devices at different locations of the distribution system. To reduce the momentary interruptions, fuse-blow scheme is used which in turn increases sustained interruption. Utilities having more concern to the sustained interruptions prefer to use fuse-save scheme over fuse-blow scheme. Different models have been developed to solve the problems incorporating placement of various combinations of protective devices in a distribution network for increasing the profit of the utility. The uncertainties in temporary failure rates, permanent failure rates, repair rates and load data have been considered in the problem formulation using three-point estimate method. A generalised objective function capable of simulating different combinations of the protective devices has also been developed. The formulated problems have been solved for 58 bus and IEEE 123 bus distribution networks using mixed integer non-linear programming optimisation technique. After analysing the test results of the various scenarios for the two test systems, it is concluded that maximum profit for the utility is obtained by using the scenario corresponding to a combination of the four protective devices, namely reclosers, switches, fuse-blow fuses and fuse-save fuses.
引用
收藏
页码:1474 / 1485
页数:12
相关论文
共 19 条
[11]   Multiobjective multistage distribution system planning using tabu search [J].
Pereira Junior, Benvindo Rodrigues ;
Cossi, Antonio Marcos ;
Contreras, Javier ;
Sanches Mantovani, Jose Roberto .
IET GENERATION TRANSMISSION & DISTRIBUTION, 2014, 8 (01) :35-45
[12]  
Safdarian A., 2016, IEEE T POWER SYSTEMS, VPP, P1
[13]   Modified shuffled frog leaping algorithm for optimal switch placement in distribution automation system using a multi-objective fuzzy approach [J].
Sardou, I. Goroohi ;
Banejad, M. ;
Hooshmand, R. ;
Dastfan, A. .
IET GENERATION TRANSMISSION & DISTRIBUTION, 2012, 6 (06) :493-502
[14]  
Short T.A., 2014, SHORT CIRCUIT PROTEC
[15]   Optimized distribution protection using binary programming [J].
Soudi, F ;
Tomsovic, K .
IEEE TRANSACTIONS ON POWER DELIVERY, 1998, 13 (01) :218-224
[16]   Probabilistic load-flow computation using point estimate method [J].
Su, CL .
IEEE TRANSACTIONS ON POWER SYSTEMS, 2005, 20 (04) :1843-1851
[17]  
Tio A. E. D. C., 2013, 2013 IEEE PES ASIA P, P1, DOI [10.1109/APPEEC.2013.6837235, DOI 10.1109/APPEEC.2013.6837235]
[18]   Placement of Remote-Controlled Switches to Enhance Distribution System Restoration Capability [J].
Xu, Yin ;
Liu, Chen-Ching ;
Schneider, Kevin P. ;
Ton, Dan T. .
IEEE TRANSACTIONS ON POWER SYSTEMS, 2016, 31 (02) :1139-1150
[19]  
Yun S.Y., 2003, POW ENG SOC GEN M 20, V1, P485