Non-unit-based planning and scheduling of repetitive construction projects

被引:21
作者
Huang, Rong-Yau
Sun, Kuo-Shun
机构
[1] Natl Cent Univ, Inst Construct Engn & Management, Jhongli 32001, Taoyuan, Taiwan
[2] Kainan Univ, Dept Air Transportat, Taoyuan 338, Taiwan
关键词
Algorithms; Construction industry; Project management; Resource management; Scheduling;
D O I
10.1061/(ASCE)0733-9364(2006)132:6(585)
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Repetitive scheduling methods are more effective than traditional critical path methods in the planning and scheduling of repetitive construction projects. Nevertheless, almost all the repetitive scheduling methods developed so far have been based oil the premise that a repetitive project is comprised of many identical production units. In this research a non-unit-based algorithm for the planning and scheduling of repetitive projects is developed. Instead of repetitive production units, repetitive or similar activity Groups are identified and employed for scheduling. The algorithm takes into consideration: (1) the logical relationship of activity groups in a repetitive project: (2) the usage of various resource crews in all activity group; (3) the maintaining of resource continuity and (4) the time and cost for the routing of resource crews. A sample case Study and a case study of a sewer system project are conducted to validate the algorithm. as well as to demonstrate its application. Results and findings are reported.
引用
收藏
页码:585 / 597
页数:13
相关论文
共 12 条
[1]   LINE-OF-BALANCE SCHEDULING IN PAVEMENT CONSTRUCTION [J].
ARDITI, D ;
ALBULAK, MZ .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (03) :411-424
[2]  
CARR RI, 1974, J CONSTRUCT DIV-ASCE, V100, P403
[3]   APPLICATION OF LINEAR SCHEDULING [J].
CHRZANOWSKI, EN ;
JOHNSTON, DW .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (04) :476-491
[4]  
El-Rayes K., 1998, Journal of Construction Management and Economics, V16, P433
[5]   Linear scheduling model: Development of controlling activity path [J].
Harmelink, DJ ;
Rowings, JE .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1998, 124 (04) :263-268
[6]   Scheduling projects with repeating activities [J].
Harris, RB ;
Ioannou, PG .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1998, 124 (04) :269-278
[7]   Cost optimization in projects with repetitive nonserial activities [J].
Hegazy, T ;
Wassef, N .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (03) :183-191
[8]  
JOHNSTON DW, 1981, J CONSTRUCT DIV-ASCE, V107, P247
[9]  
OBRIEN JJ, 1975, J CONSTRUCT DIV-ASCE, V101, P895
[10]   RPM - REPETITIVE PROJECT MODELING [J].
REDA, RM .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1990, 116 (02) :316-330