A fuzzy buffer setting method for project scheduling under uncertainty

被引:0
|
作者
Zhou, Yikun [1 ]
机构
[1] Tongji Univ, Sch Econ & Management, Shanghai 200092, Peoples R China
来源
ADVANCES IN ENERGY SCIENCE AND TECHNOLOGY, PTS 1-4 | 2013年 / 291-294卷
关键词
Project scheduling; Buffer setting; Fuzzy; TRADE-OFF; STABILITY; MAKESPAN;
D O I
10.4028/www.scientific.net/AMM.291-294.2889
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
The buffer setting methods are useful ways to deal with the uncertainty. However, few has concern how to estimate the safe time of each project activity, which is used to set the buffer, when historic information of project is not enough. In this paper a fuzzy buffer setting method is proposed to solve the shortage. The fuzzy method has three steps: estimate the fuzzy duration, calculate the safe time and determine the buffer size. A calculation example is also given to introduce the detail procedure of this method.
引用
收藏
页码:2889 / 2894
页数:6
相关论文
共 50 条
  • [1] Key Chain Buffer Setting Method for Uncertainty of Project Duration
    Zhang, Fenglin
    Gao, Xingming
    MAN-MACHINE-ENVIRONMENT SYSTEM ENGINEERING, MMESE 2018, 2019, 527 : 593 - 599
  • [2] Reactive project scheduling method to enhance project progress under uncertainty
    Suwa, Haruhiko
    Morita, Daisuke
    JOURNAL OF ADVANCED MECHANICAL DESIGN SYSTEMS AND MANUFACTURING, 2016, 10 (03):
  • [3] Project scheduling under uncertainty using fuzzy modelling and solving techniques
    Masmoudi, Malek
    Hait, Alain
    ENGINEERING APPLICATIONS OF ARTIFICIAL INTELLIGENCE, 2013, 26 (01) : 135 - 149
  • [4] Buffer size setting method for DBR scheduling
    Central R and D Center, Telemetries Team, LS Industrial Systems Co., Ltd., 533 Hogae-dong, Anyane-Shi, Kyongki-Do 431-080, Korea, Republic of
    不详
    不详
    不详
    IEEJ Trans. Electron. Inf. Syst., 2007, 3 (416-424): : 416 - 424
  • [5] Fuzzy Activity Network Method for Project Scheduling Under Resource Constraints
    Luong Duc Long
    Ohsato, Ario
    JOURNAL OF ADVANCED COMPUTATIONAL INTELLIGENCE AND INTELLIGENT INFORMATICS, 2007, 11 (08) : 914 - 921
  • [6] An improved project buffer sizing approach to critical chain management under resources constraints and fuzzy uncertainty
    Shi, Qian
    Gong, Ting
    2009 INTERNATIONAL CONFERENCE ON ARTIFICIAL INTELLIGENCE AND COMPUTATIONAL INTELLIGENCE, VOL I, PROCEEDINGS, 2009, : 486 - 490
  • [7] Method of Project Scheduling under Fuzzy Estimation of Durations and Precedence Relationships of Activities
    Tseng, H. S.
    Chiou, H. W.
    CRIOCM2009: INTERNATIONAL SYMPOSIUM ON ADVANCEMENT OF CONSTRUCTION MANAGEMENT AND REAL ESTATE, VOLS 1-6, 2009, : 1914 - 1922
  • [8] A hybrid projection method for resource-constrained project scheduling problem under uncertainty
    Aramesh, Saeed
    Aickelin, Uwe
    Khorshidi, Hadi Akbarzadeh
    NEURAL COMPUTING & APPLICATIONS, 2022, 34 (17): : 14557 - 14576
  • [9] A hybrid projection method for resource-constrained project scheduling problem under uncertainty
    Saeed Aramesh
    Uwe Aickelin
    Hadi Akbarzadeh Khorshidi
    Neural Computing and Applications, 2022, 34 : 14557 - 14576
  • [10] Introduction to the special issue: project scheduling under uncertainty
    Demeulemeester, Erik
    Herroelen, Willy
    JOURNAL OF SCHEDULING, 2007, 10 (03) : 151 - 152