A two-stage flow shop batch-scheduling problem with the option of using Not-All-Machines

被引:13
|
作者
Gerstl, Enrique [1 ]
Mosheiov, Gur [1 ]
机构
[1] Hebrew Univ Jerusalem, Sch Business Adm, IL-91905 Jerusalem, Israel
关键词
Scheduling; Flowshop; Makespan; Dynamic programming; Heuristic; Not-All-Machines; ALGORITHM; NUMBER; JOBS;
D O I
10.1016/j.ijpe.2013.06.018
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The decision whether to use all the available machines in the shop becomes very relevant when the capacity exceeds the demand. In such cases, it might be optimal to use only a subset of the machines. We study this option in a two-stage flowshop environment. Jobs are assumed to be identical, and are processed in batches, where a machine-dependent setup time is required when starting a new batch. The objective function is minimum makespan. We introduce an exact efficient dynamic programming algorithm, which is shown numerically to be able to solve medium size instances in very reasonable time. For the solution of large instances, we propose an asymptotically optimal heuristic procedure and a lower bound on the makespan value, which produce extremely small optimality gaps. (C) 2013 Elsevier B.V. All rights reserved.
引用
收藏
页码:161 / 166
页数:6
相关论文
共 50 条
  • [1] A TWO-STAGE FLOW SHOP SCHEDULING WITH A CRITICAL MACHINE AND BATCH AVAILABILITY
    Gerstl, Enrique
    Mosheiov, Gur
    FOUNDATIONS OF COMPUTING AND DECISION SCIENCES, 2012, 37 (01) : 39 - 56
  • [2] A note on the two-stage assembly flow shop scheduling problem with uniform parallel machines
    Koulamas, Christos
    Kyparisis, George J.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 182 (02) : 945 - 951
  • [3] Two-stage flow shop scheduling with dedicated machines
    Lin, Bertrand M. T.
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2015, 53 (04) : 1094 - 1097
  • [4] A new complexity proof for the two-stage hybrid flow shop scheduling problem with dedicated machines
    Yang, Jaehwan
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2010, 48 (05) : 1531 - 1538
  • [5] A two-stage flow shop scheduling problem with transportation considerations
    Nacira Chikhi
    Moncef Abbas
    Rachid Benmansour
    Abdelghani Bekrar
    Saïd Hanafi
    4OR, 2015, 13 : 381 - 402
  • [6] A two-stage flow shop scheduling problem with transportation considerations
    Chikhi, Nacira
    Abbas, Moncef
    Benmansour, Rachid
    Bekrar, Abdelghani
    Hanafi, Said
    4OR-A QUARTERLY JOURNAL OF OPERATIONS RESEARCH, 2015, 13 (04): : 381 - 402
  • [7] On the two-stage assembly flow shop problem
    Hadda, Hatem
    Dridi, Najoua
    Hajri-Gabouj, Sonia
    TOP, 2024, 32 (02) : 224 - 244
  • [8] A two-stage flexible flow-shop scheduling problem with m identical parallel machines on one stage and a batch processor on the other stage
    何龙敏
    孙世杰
    程明宝
    Journal of Harbin Institute of Technology, 2008, (05) : 674 - 678
  • [9] Scheduling rules for two-stage flexible flow shop scheduling problem subject to tail group constraint
    Li, Zhan-tao
    Chen, Qing-xin
    Mao, Ning
    Wang, Xiaoming
    Liu, Jianjun
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2013, 146 (02) : 667 - 678
  • [10] Research on Two-Stage Hybrid Flow Shop Scheduling with Contiguous Machines
    Zhang Minghui
    Li Xiaofei
    2019 INTERNATIONAL CONFERENCE ON ROBOTS & INTELLIGENT SYSTEM (ICRIS 2019), 2019, : 458 - 461