Time/cost optimization using hybrid evolutionary algorithm in construction project scheduling

被引:52
|
作者
Rogalska, Magdalena [2 ]
Bozejko, Wojciech [1 ]
Hejducki, Zdzislaw [1 ]
机构
[1] Wroclaw Univ Technol, PL-50370 Wroclaw, Poland
[2] Tech Univ Lublin, PL-20950 Lublin, Poland
关键词
Time coupling methods (TCM); Hybrid evolutionary algorithm (HEA); Time/cost relationship;
D O I
10.1016/j.autcon.2008.04.002
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper deals with construction project scheduling. In the literature on the subject one can find such scheduling methods as: the Linear Scheduling Model (LSM), Line of Balance (LOB) charts and CMP/PERT network planning. The methods take into account several objective functions: the least cost, the least time, limited resources, work priorities, etc., both in the deterministic and probabilistic approach. The paper presents an analysis of the time/cost relationship, performed using time coupling method TCM III. A modified hybrid evolutionary algorithm (HEA) developed by Bozejko and Wodecki (A Hybrid Evolutionary Algorithm for Some Discrete Optimization Problems. IEEE Computer Society, 325-331, 2005) was used for optimization. (C) 2008 Elsevier B.V. All rights reserved.
引用
收藏
页码:24 / 31
页数:8
相关论文
共 50 条
  • [1] Multicriteria construction project scheduling method using evolutionary algorithm
    Piotr Jaskowski
    Anna Sobotka
    Operational Research, 2006, 6 (3) : 283 - 297
  • [2] Project time–cost trade-off scheduling: a hybrid optimization approach
    Hadi Mokhtari
    Abdollah Aghaie
    Javad Rahimi
    Ashkan Mozdgir
    The International Journal of Advanced Manufacturing Technology, 2010, 50 : 811 - 822
  • [3] Scheduling construction projects using evolutionary algorithm
    Jaskowski, Piotr
    Sobotka, Anna
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2006, 132 (08): : 861 - 870
  • [4] A hybrid evolutionary algorithm for the resource constrained project scheduling problem
    Thammano, Arit
    Phu-ang, Ajchara
    PROCEEDINGS OF THE SEVENTEENTH INTERNATIONAL SYMPOSIUM ON ARTIFICIAL LIFE AND ROBOTICS (AROB 17TH '12), 2012, : 834 - 837
  • [5] Project time-cost trade-off scheduling: a hybrid optimization approach
    Mokhtari, Hadi
    Aghaie, Abdollah
    Rahimi, Javad
    Mozdgir, Ashkan
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 50 (5-8): : 811 - 822
  • [6] Optimization of Total Holding Cost in Job shop scheduling by using Hybrid Algorithm
    Gobinath, S.
    Arumugam, C.
    Ramya, G.
    Chandrasekaran, M.
    ADVANCED MANUFACTURING RESEARCH AND INTELLIGENT APPLICATIONS, 2014, 591 : 176 - +
  • [7] A hybrid evolutionary algorithm for the resource-constrained project scheduling problem
    Thammano A.
    Phu-ang A.
    Artificial Life and Robotics, 2012, 17 (02) : 312 - 316
  • [8] Hybrid evolutionary algorithm for large-scale project scheduling problems
    Zaman, Forhad
    Elsayed, Saber
    Sarker, Ruhul
    Essam, Daryl
    COMPUTERS & INDUSTRIAL ENGINEERING, 2020, 146
  • [9] Hybrid evolutionary algorithm with marriage of genetic algorithm and extremal optimization for production scheduling
    Yu-Wang Chen
    Yong-Zai Lu
    Gen-Ke Yang
    The International Journal of Advanced Manufacturing Technology, 2008, 36 : 959 - 968
  • [10] Hybrid evolutionary algorithm with marriage of genetic algorithm and extremal optimization for production scheduling
    Chen, Yu-Wang
    Lu, Yong-Zai
    Yang, Gen-Ke
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2008, 36 (9-10): : 959 - 968