Solution algorithms for dynamic lot-sizing in remanufacturing systems

被引:17
作者
Ahn, Hyung-Dae [1 ]
Lee, Dong-Ho [1 ]
Kim, Hwa-Joong [2 ]
机构
[1] Hanyang Univ, Dept Ind Engn, Seoul 133791, South Korea
[2] Inha Univ, Grad Sch Logist, Inchon 402751, South Korea
关键词
remanufacturing; dynamic lot-sizing; dynamic programming; heuristics; PRODUCT RECOVERY; PLANNING-MODEL; CAPACITY;
D O I
10.1080/00207543.2010.535038
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We consider the problem of determining the lot sizes that satisfy the demands of remanufactured products over a given planning horizon with discrete time periods. Remanufacturing, in which used or end-of-life products are restored to like-new condition, typically consists of disassembly, reprocessing and reassembly processes, and hence the lot sizes are determined for each of the three processes. The objective is to minimise the sum of setup and inventory holding costs occurring at the three processes. To represent the problem mathematically, we suggest a mixed integer programming model by combining the existing ones for disassembly and assembly systems. After proving that the problem is NP-hard, we suggest two dynamic programming based heuristics, called the aggregation and the decomposition type heuristics in this paper. Computational experiments were done on various test instances, and the results show that the two heuristics give near-optimal solutions in a short amount of computation time. Also, the performances of the heuristics are compared according to different values of problem parameters.
引用
收藏
页码:6729 / 6748
页数:20
相关论文
共 30 条
  • [1] COMPUTATIONAL-COMPLEXITY OF UNCAPACITATED MULTI-ECHELON PRODUCTION PLANNING PROBLEMS
    ARKIN, E
    JONEJA, D
    ROUNDY, R
    [J]. OPERATIONS RESEARCH LETTERS, 1989, 8 (02) : 61 - 66
  • [2] Lot sizing in reverse MRP for scheduling disassembly
    Barba-Gutierrez, Y.
    Adenso-Diaz, B.
    Gupta, S. M.
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2008, 111 (02) : 741 - 751
  • [3] Barba-Gutierrez Y., 2009, INT J ADV MANUF TECH, V40, P413
  • [4] CLEGG AJ, 1995, PROCEEDINGS OF THE 1995 IEEE INTERNATIONAL SYMPOSIUM ON ELECTRONICS AND THE ENVIRONMENT - ISEE, P186, DOI 10.1109/ISEE.1995.514973
  • [5] Generic production planning model for remanufacturing systems
    Doh, H-H
    Lee, D-H
    [J]. PROCEEDINGS OF THE INSTITUTION OF MECHANICAL ENGINEERS PART B-JOURNAL OF ENGINEERING MANUFACTURE, 2010, 224 (B1) : 159 - 168
  • [6] Remanufacturing of mobile phones-capacity, program and facility adaptation planning
    Franke, C
    Basdere, B
    Ciupek, M
    Seliger, S
    [J]. OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2006, 34 (06): : 562 - 570
  • [7] Economic lot-sizing with remanufacturing options
    Golany, B.
    Yang, J.
    Yu, G.
    [J]. IIE Transactions (Institute of Industrial Engineers), 2001, 33 (11): : 995 - 1003
  • [8] Production planning and control for remanufacturing: industry practice and research needs
    Guide, VDR
    [J]. JOURNAL OF OPERATIONS MANAGEMENT, 2000, 18 (04) : 467 - 483
  • [9] Production planning for closed-loop supply chains with product recovery and reuse: an analytical approach
    Jayaraman, V
    [J]. INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2006, 44 (05) : 981 - 998
  • [10] Kim H.- J., 2007, INT J PROD RES, V45, P4465