Hybrid meta-heuristic methods for the multi-resource leveling problem with activity splitting

被引:20
作者
Alsayegh, Hadeel [1 ]
Hariga, Mortcer [1 ]
机构
[1] Amer Univ Sharjah, Coll Engn, Engn Syst Management Grad Program, Sharjah, U Arab Emirates
关键词
Resource leveling; Activity splitting; Meta-heuristics; Particle swarm optimization; Simulated annealing; CONSTRUCTION;
D O I
10.1016/j.autcon.2012.04.017
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In this paper, we consider the multi-resource leveling problem with the objective of minimizing the total costs resulting from the variation of the resource utilization and the cost of splitting non-critical activities. We propose hybrid meta-heuristic methods which combine particle swarm optimization (PSO) and simulated annealing (SA) search procedures to generate near-optimal project schedules in less computational time than the exact optimization procedure. The PSO algorithms are based on different update mechanisms for the particles' velocities and positions. The cost and computation time performances of the combined PSO/SA search procedures are evaluated using a set of benchmark problems. Based on the results of the computational experiments, we suggest one of the proposed heuristic procedures to be used for solving the multi-resource leveling problem with activity splitting. (C) 2012 Elsevier B.V. All rights reserved.
引用
收藏
页码:89 / 98
页数:10
相关论文
共 19 条
[1]  
[Anonymous], 1987, SIMULATED ANNEALING
[2]   OPTIMAL RESOURCE LEVELING USING NON-SERIAL DYNAMIC-PROGRAMMING [J].
BANDELLONI, M ;
TUCCI, M ;
RINALDI, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1994, 78 (02) :162-177
[3]   RESOURCE LEVELING IN CONSTRUCTION BY OPTIMIZATION [J].
EASA, SM .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02) :302-316
[4]   Evolutionary resource scheduler for linear projects [J].
Georgy, Maged E. .
AUTOMATION IN CONSTRUCTION, 2008, 17 (05) :573-583
[5]   Cost Optimization Model for the Multiresource Leveling Problem with Allowed Activity Splitting [J].
Hariga, Moncer ;
El-Sayegh, Sameh M. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2011, 137 (01) :56-64
[6]  
Harris R.B., 1978, Precedence and Arrow Networking Techniques for Construction
[7]   Modification of minimum moment approach in resource leveling [J].
Hiyassat, MAS .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2000, 126 (04) :278-284
[8]   RESOURCE-MANAGEMENT IN CONSTRUCTION [J].
KARAA, FA ;
NASR, AY .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1986, 112 (03) :346-357
[9]  
Kennedy J, 1997, IEEE SYS MAN CYBERN, P4104, DOI 10.1109/ICSMC.1997.637339
[10]  
Kennedy J, 1995, 1995 IEEE INTERNATIONAL CONFERENCE ON NEURAL NETWORKS PROCEEDINGS, VOLS 1-6, P1942, DOI 10.1109/icnn.1995.488968