The accuracy of preliminary cost estimates in Public Works Department (PWD) of Peninsular Malaysia

被引:25
作者
Azman, Mohd Azrai [1 ]
Abdul-Samad, Zulkiflee [2 ]
Ismail, Suraya [2 ]
机构
[1] Univ Teknol MARA UiTM, Fac Architecture Planning & Surveying, Dept Quant Surveying, Kota Samarahan 94300, Sarawak, Malaysia
[2] Univ Malaya, Fac Built Environm, Dept Quant Surveying, Kuala Lumpur 50603, Malaysia
关键词
Public construction; Budget cost estimate; Quantity Surveyors; Tendering; Malaysia; PROJECTS;
D O I
10.1016/j.ijproman.2012.11.008
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
This paper presents the accuracy of preliminary cost estimates prepared by Public Works Department (PWD), which is the largest public construction management in Malaysia. It attempts to understand the Quantity Surveyors' (QS) estimation accuracy in relation to public projects. This study analyses 83 projects of estimates and tender bids. The analysis includes three (3) estimating targets i.e. lowest bid, accepted bid and mean of the bids. To broaden the study, 344 QS involved in the procurement answered the questionnaires. Linear multiple regression analysis on project characteristics shows that project size, number of bidders, location and type of schools affect the bias. Contract period affects the consistency. The use of mean of the bids is the best-fit target to explain the bias in terms of adjusted R-2. The accuracy may improve if sufficient design information is available, proper cost planning and improving the application of historical cost data. As an alternative, the phenomenon of overestimation is resulted from government directive instruction, which could challenge the rational of accurate estimate. (C) 2012 Elsevier Ltd. APM and IPMA. All rights reserved.
引用
收藏
页码:994 / 1005
页数:12
相关论文
共 71 条
[1]  
Abdul-Aziz Abdul-Rashid., 2004, Structural Survey, V22, P53
[2]   Estimating the cost of capital projects: an empirical study of accuracy levels for municipal government projects [J].
AbouRizk, SM ;
Babey, GM ;
Karumanasseri, G .
CANADIAN JOURNAL OF CIVIL ENGINEERING, 2002, 29 (05) :653-661
[3]   The accuracy of pre-tender building cost estimates in Australia [J].
Aibinu, Ajibade Ayodeji ;
Pasco, Thomas .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2008, 26 (12) :1257-1269
[4]  
Ashworth A., 2010, COST STUDIES BUILDIN, V5th
[5]  
Ashworth A., 1982, Accuracy in estimating, P412
[6]  
Boussabaine A.:., 2016, Cost Planning of PFI and PPP Building Projects
[7]   Investigation of bid price competition measured through prebid project estimates, actual bid prices, and number of bidders [J].
Carr, PG .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2005, 131 (11) :1165-1172
[8]  
Chappell D., 2001, Building contract dictionary
[9]   A study of clients' and estimators' tolerance towards estimating errors [J].
Cheung, Franco K. T. ;
Wong, Margie W. L. ;
Skitmore, Martin .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2008, 26 (04) :349-362
[10]  
Dattalo P., 2008, Pocket guide to social work research methods: determining sample size: balancing power, precision and practicality