Task-failure-driven rebalancing of disassembly lines

被引:121
作者
Altekin, F. Tevhide [1 ]
Akkan, Can [1 ]
机构
[1] Sabanci Univ, Sabanci Sch Management, Istanbul, Turkey
关键词
line balancing; disassembly; predictive-reactive rebalancing; task failures; REVERSE SUPPLY CHAINS; PRODUCT RECOVERY; ISSUES; ALGORITHM; MODEL; CLASSIFICATION; OPTIMIZATION; OPPORTUNITY; MANAGEMENT; QUALITY;
D O I
10.1080/00207543.2011.616915
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Many reverse-logistics systems that collect and reprocess end-of-life products require a disassembly stage. The variability of incoming products and the extent of damage, which is more likely to occur during disassembly than assembly, create significant uncertainty in disassembly tasks, namely the possibility of failed tasks. Such failures may lead to some successor tasks being infeasible, which changes the work content of downstream stations. To improve the profitability of such a disassembly line, a mixed-integer-programming-based, predictive-reactive approach is proposed. In the first step, a predictive balance is created and then, in the second step, given a task failure, the tasks of the disassembled product with that task failure are re-selected and re-assigned to the stations (i.e. the line is rebalanced). In the second step, the objective function models both the profit obtained from the disassembled product and the possible increase in any station's workload beyond the predictive cycle time. Since this rebalancing approach affects the work content of stations, a discrete-event simulation study is also carried out to analyse and compare the performance of disassembly lines for optimally found line balances (predictive and reactive). The results show that, with the proposed approach, 24-32% of the monetary throughput lost due to not taking corrective action can be recovered.
引用
收藏
页码:4955 / 4976
页数:22
相关论文
共 60 条
[1]   A collaborative ant colony algorithm to stochastic mixed-model U-shaped disassembly line balancing and sequencing problem [J].
Agrawal, S. ;
Tiwari, M. K. .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2008, 46 (06) :1405-1429
[2]   Profit-oriented disassembly-line balancing [J].
Altekin, F. Tevhide ;
Kandiller, Levent ;
Ozdemirel, Nur Evin .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2008, 46 (10) :2675-2693
[3]   Executing production schedules in the face of uncertainties: A review and some future directions [J].
Aytug, H ;
Lawley, MA ;
McKay, K ;
Mohan, S ;
Uzsoy, R .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 161 (01) :86-110
[4]   A survey on problems and methods in generalized assembly line balancing [J].
Becker, C ;
Scholl, A .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2006, 168 (03) :694-715
[5]   Future disassembly and recycling technology - Results of a Delphi study [J].
Boks, C ;
Tempelman, E .
FUTURES, 1998, 30 (05) :425-442
[6]   Assembly line balancing: Which model to use when? [J].
Boysen, Nils ;
Fliedner, Malte ;
Scholl, Armin .
INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2008, 111 (02) :509-528
[7]   A classification of assembly line balancing problems [J].
Boysen, Nils ;
Fliedner, Malte ;
Scholl, Armin .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2007, 183 (02) :674-693
[8]   OPERATIONS PLANNING ISSUES IN AN ASSEMBLY DISASSEMBLY ENVIRONMENT [J].
BRENNAN, L ;
GUPTA, SM ;
TALEB, KN .
INTERNATIONAL JOURNAL OF OPERATIONS & PRODUCTION MANAGEMENT, 1994, 14 (09) :57-67
[9]  
Dar-El E.M., 1991, INT J PROD ECON, V25, P103
[10]   BALANCING CYCLE TIME AND WORKSTATIONS [J].
DECKRO, RF .
IIE TRANSACTIONS, 1989, 21 (02) :106-111