A discrete event simulation approach for mine development planning at Codelco's New Mine Level

被引:1
作者
Soto, I [1 ]
Anani, A. [2 ]
Cordova, E. [1 ]
机构
[1] Pontificia Univ Catolica Chile, Dept Min Engn, Santiago, Chile
[2] Univ Arizona, Dept Min & Geol Engn, Tucson, AZ 85721 USA
关键词
mine development; discrete event simulation; OR in natural resources; mine planning caving; OPTIMIZATION; SYSTEMS; TRUCK;
D O I
10.17159/2411-9717/2045/2022
中图分类号
TF [冶金工业];
学科分类号
0806 ;
摘要
The new caving megaprojects that are planned to go into production in the next decade have scheduled horizontal developments at very high rates, which are difficult to achieve. Research has been conducted that seeks to model the construction times for underground developments to determine the feasibility of achieving the planned rates. However, these previous attempts do not consider all the operational aspects that make up the mine development cycle. Here, we present a discrete event simulation (DES) model that individualizes each unit operation of the development cycle to determine the construction rates that new projects will be able to attain. The developed model was applied to the New Mine Level (NML) of the El Teniente Division (DET). The results indicate that it would be impractical to achieve the advance rates scheduled in the original plans if the unit operations of the mine continue to be executed using the status quo. The metres developed after six years in the sections analysed can be significantly improved by changing the maintenance strategy for the equipment (457 metres increase), orepass availability (194 metres increase), and the initial planning sequence (1 598 metres increase). It is recommended that the mine implements a flexible maintenance strategy, defines a strategy to ensure and increase orepass availability to contractors, and makes use of current simulation tools for a more robust development sequence planning.
引用
收藏
页码:549 / 559
页数:11
相关论文
共 37 条
  • [1] A comparison between Offset Herringbone and El Teniente underground cave mining extraction layouts using a discrete event simulation technique
    Ahmed, Haitham M.
    Scoble, Malcolm J.
    Dunbar, W. Scott
    [J]. INTERNATIONAL JOURNAL OF MINING RECLAMATION AND ENVIRONMENT, 2016, 30 (02) : 71 - 91
  • [2] Anani Angelina, 2017, International Journal of Mining and Mineral Engineering, V8, P96
  • [3] Optimizing cut-out distance for maximum coal productivity
    Anani, Angelina
    Nyaaba, Wedam
    Hekmat, Asieh
    Cordova, Eduardo A.
    [J]. SIMULATION-TRANSACTIONS OF THE SOCIETY FOR MODELING AND SIMULATION INTERNATIONAL, 2019, 95 (06): : 545 - 559
  • [4] Bala R.J., 2018, MATH MODELLING ENG P, V5, P116, DOI [10.18280/mmep.050209, DOI 10.18280/MMEP.050209]
  • [5] Estimation of reliability-based maintenance time intervals of Load-Haul-Dumper in an underground coal mine
    Balaraju, J.
    Raj, M. Govinda
    Murthy, C. H. S. N.
    [J]. JOURNAL OF MINING AND ENVIRONMENT, 2018, 9 (03): : 761 - 770
  • [6] Basu A., 1999, INT J SURFACE MINING, V13, P79, DOI [10.1080/09208119908944214, DOI 10.1080/09208119908944214]
  • [7] CCATAMAYO BARRIOS J.H., 2017, THESIS U CHILE SANTI
  • [8] CHAMI J., 2012, THESIS U CHILE SANTI
  • [9] COCHILCO, 2019, AN EST COBR OTR MIN
  • [10] CODELCO, 2020, MEM AN 2019