Visualizing high-rise building construction strategies using linear scheduling and 4D CAD

被引:62
|
作者
Russell, Alan [1 ]
Staub-French, Sheryl [1 ]
Tran, Ngoc [1 ]
Wong, William [1 ]
机构
[1] Univ British Columbia, Dept Civil Engn, Vancouver, BC V6T 1Z4, Canada
关键词
4D CAD; Linear scheduling; Product modeling; Three-dimensional models; Building information models; Scheduling; Visualization;
D O I
10.1016/j.autcon.2008.08.001
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Project teams face ever increasing pressure to deliver projects as quickly as possible. To meet these demands, contractors are faced with the need to explore various construction strategies in order to meet delivery dates, and to assure themselves as to the achievability and quality of a schedule. Various visual representations of a project's schedule and associated information combined with visual representations of the project in progress, i.e. 4D CAD, can assist with these tasks of identifying effective construction strategies for shortening project duration, assessing their workability, and judging schedule quality. Such visual representations aid communication amongst project staff and facilitate brain-storming, and, implemented well they can provide clear. fast, and multi-climensional feedback to the project team. In this paper, we describe aspects of our work which is directed at formulating a dynamic visualization environment that links 3D CAD, a generalization of traditional CPM which embraces linear scheduling, dual product representations (scheduling and CAD system) and their mapping onto each other, and schedule and CAD graphics in a manner which facilitates the relatively rapid exploration of alternative construction method and scheduling strategies for large scale linear projects (e.g. high-rise buildings, bridges, etc.). Requirements of such an environment include quickness, treating scale, working at multiple levels of detail, dealing with design variability. and realistic representation of the work. Use is made of a realistic example to highlight aspects of our approach and identify important issues that must be addressed if a visualization environment useful for construction professionals is to be developed. (C) 2008 Elsevier B.V. All rights reserved.
引用
收藏
页码:219 / 236
页数:18
相关论文
共 30 条
  • [1] Linear scheduling and 4D visualization
    Staub-French, Sheryl
    Russel, Alan
    Tran, Ngoc
    JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2008, 22 (03) : 192 - 205
  • [2] Using 4D CAD to visualize the impacts of highway construction on the public
    Zanen, P. P. A.
    Hartmann, T.
    Al-Jibouri, S. H. S.
    Heijmans, H. W. N.
    AUTOMATION IN CONSTRUCTION, 2013, 32 : 136 - 144
  • [3] An evaluation of the applicability of 4D CAD on construction projects
    Mahalingam, Ashwin
    Kashyap, Rahul
    Mahajan, Charudatta
    AUTOMATION IN CONSTRUCTION, 2010, 19 (02) : 148 - 159
  • [4] 4D CAD models to support the coordination of construction activities between contractors
    Trebbe, Martijn
    Hartmann, Timo
    Doree, Andre
    AUTOMATION IN CONSTRUCTION, 2015, 49 : 83 - 91
  • [5] Scheduling model for repetitive construction processes for high-rise buildings
    Cho, Kyuman
    Hong, Taehoon
    Hyun, Changtaek
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2011, 38 (01) : 36 - 48
  • [6] 4D Modeling and Simulation for the Teaching of Structural Principles and Construction Techniques Towards modeling and visualization guidelines for high-rise buildings
    Kubicki, Sylvain
    Guerriero, Annie
    Leclercq, Pierre
    Nys, Koenraad
    Halin, Gilles
    ECAADE 2012, VOL 1: DIGITAL PHYSICALITY, 2012, : 87 - 95
  • [7] Integrated Offsite Logistics Scheduling Approach for High-Rise Modular Building Projects
    Yang, Yi
    Pan, Mi
    Pan, Wei
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2022, 148 (06)
  • [8] Investigating the Human Errors in 4D BIM Construction Scheduling
    Kandregula, Shravan Kumar
    Le, Tuyen
    CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 750 - 757
  • [9] Construction Management Utilizing 4D CAD and Operations Simulation Methodologies
    张建平
    张洋
    胡振中
    鹿明
    Tsinghua Science and Technology, 2008, (S1) : 241 - 247
  • [10] Construction Management Utilizing 4D CAD and Operations Simulation Methodologies
    Zhang, Jianping
    Zhang, Yang
    Hu, Zhenzhong
    Lu, Ming
    Tsinghua Science and Technology, 2008, 13 (SUPPL. 1): : 241 - 247