4D CAD model updating using image processing-based construction progress monitoring

被引:90
作者
Kim, Changyoon [1 ]
Kim, Byoungil [1 ]
Kim, Hyoungkwan [1 ]
机构
[1] Yonsei Univ, Dept Civil Engn, Seoul 120749, South Korea
基金
新加坡国家研究基金会;
关键词
3D CAD; 4D CAD; Cable-stayed bridge; Image processing; Progress monitoring; Project scheduling; APPLICABILITY; MANAGEMENT;
D O I
10.1016/j.autcon.2013.03.005
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
For a four-dimensional (4D) computer-aided design (CAD) model to be useful for users throughout a construction project, the model must be updated in a timely and accurate manner during the construction. Only when it has been properly updated can the 4D CAD model reflect the real progress of a construction site to inform managerial decision making. However, updating a 4D CAD model is time-consuming and labor-intensive because the full updating process, from site data acquisition to 4D model regeneration, is typically conducted manually. This difficulty in updating a 4D model discourages industry practitioners from actively adopting 4D models. This paper presents an image processing-based methodology for the automatic updating of a 4D CAD model. Characterized by 3D CAD-based image mask filters, color-based noise removal, and area-based progress calculation, the image processing approach provides as-built schedule information. The schedule information is then automatically integrated with an existing 3D CAD model in batch-processing modes to produce the updated 4D CAD model. The proposed methodology was applied and verified in a cable-stayed bridge construction project and is expected to facilitate the wider use of 4D CAD models in the construction industry. (c) 2013 Elsevier B.V. All rights reserved.
引用
收藏
页码:44 / 52
页数:9
相关论文
共 19 条
  • [1] Automated Object Identification Using Optical Video Cameras on Construction Sites
    Chi, Seokho
    Caldas, Carlos H.
    [J]. COMPUTER-AIDED CIVIL AND INFRASTRUCTURE ENGINEERING, 2011, 26 (05) : 368 - 380
  • [2] RFID+4D CAD for progress management of structural steel works in high-rise buildings
    Chin, Sangyoon
    Yoon, Suwon
    Choi, Cheolho
    Cho, Changyon
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2008, 22 (02) : 74 - 89
  • [3] Integrated Sequential As-Built and As-Planned Representation with D4AR Tools in Support of Decision-Making Tasks in the AEC/FM Industry
    Golparvar-Fard, Mani
    Pena-Mora, Feniosky
    Savarese, Silvio
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2011, 137 (12) : 1099 - 1116
  • [4] Halpin DanielW., 2006, Construction Management, V3rd
  • [5] RFID and CCTV-Based Material Delivery Monitoring for Cable-Stayed Bridge Construction
    Ju, Yeonjong
    Kim, Changyoon
    Kim, Hyoungkwan
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2012, 26 (02) : 183 - 190
  • [6] Empirical study on the merit of web-based 4D visualization in collaborative construction planning and scheduling
    Kang, Julian H.
    Anderson, Stuart D.
    Clayton, Mark J.
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2007, 133 (06) : 447 - 461
  • [7] Applicability of 4D CAD in Civil Engineering Construction: Case Study of a Cable-Stayed Bridge Project
    Kim, Changyoon
    Kim, Hyoungkwan
    Park, Taekwun
    Kim, Moon Kyum
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2011, 25 (01) : 98 - 107
  • [8] Feasibility study of 4D CAD in commercial construction
    Koo, B
    Fischer, M
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2000, 126 (04): : 251 - 260
  • [9] Application of 4D for dynamic site layout and management of construction projects
    Ma, ZY
    Shen, QP
    Zhang, JP
    [J]. AUTOMATION IN CONSTRUCTION, 2005, 14 (03) : 369 - 381
  • [10] An evaluation of the applicability of 4D CAD on construction projects
    Mahalingam, Ashwin
    Kashyap, Rahul
    Mahajan, Charudatta
    [J]. AUTOMATION IN CONSTRUCTION, 2010, 19 (02) : 148 - 159