Bi-objective Optimization of RCPSP under Time-of-use Electricity Tariffs

被引:2
作者
He, Lihua [1 ]
Zhang, Yajun [1 ]
机构
[1] China Univ Petr East China, Sch Econ & Management, Qingdao 266580, Shandong, Peoples R China
基金
中国国家自然科学基金;
关键词
Resource-constrained project scheduling problem; Time-of-use electricity tariffs; Bi-objective optimization; NSGA-II algorithm; Labor shift differential payments; PROJECT SCHEDULING PROBLEM; TOTAL-ENERGY CONSUMPTION; DEMAND-SIDE MANAGEMENT; SINGLE-MACHINE; EFFICIENCY; ALGORITHM; INDICATORS; FRAMEWORK; IMPACTS; SOLVE;
D O I
10.1007/s12205-022-0095-4
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In recent years, to alleviate the peak load of the power grid, many countries have implemented time-of-use (TOU) electricity tariffs. When both manpower and equipment are needed to perform project activities, wage and electricity costs become the main components of the total project cost. High-power activities can be implemented during off-peak periods to reduce energy costs and peak demand for electricity. Labor shift differential payments will increase wage costs for off-peak labor overtime. This paper proposes a bi-objective mixed-integer nonlinear programming model for resource-constrained project scheduling problems under TOU. Machine-level decisions are made to minimize total project cost and completion time. This model has an enormous solution space when there are many tasks and long durations, especially when the time granularity is small, which is not conducive to an accurate solution. Therefore, an improved NSGA-II algorithm is presented to effectively solve the model. The results show that the proposed model and algorithm can effectively reduce the total project cost and construction period while reducing peak power demand.
引用
收藏
页码:4971 / 4983
页数:13
相关论文
共 39 条
[11]   Demand side management of industrial electricity consumption: Promoting the use of renewable energy through real-time pricing [J].
Finn, Paddy ;
Fitzpatrick, Colin .
APPLIED ENERGY, 2014, 113 :11-21
[12]   Resource Constrained Project Scheduling by Harmony Search Algorithm [J].
Giran, Omer ;
Temur, Rasim ;
Bekdas, Gebrail .
KSCE JOURNAL OF CIVIL ENGINEERING, 2017, 21 (02) :479-487
[13]   Resource-constrained project scheduling problem: review of past and recent developments [J].
Habibi, Farhad ;
Barzinpour, Farnaz ;
Sadjadi, Seyed Jafar .
JOURNAL OF PROJECT MANAGEMENT, 2018, 3 (02) :55-88
[14]   Integration of production scheduling and energy-cost optimization using Mean Value Cross Decomposition [J].
Hadera, Hubert ;
Ekstrom, Joakim ;
Sand, Guido ;
Mantysaari, Juha ;
Harjunkoski, Iiro ;
Engell, Sebastian .
COMPUTERS & CHEMICAL ENGINEERING, 2019, 129
[15]   An efficient genetic algorithm to solve the resource-constrained project scheduling problem with transfer times: The single mode case [J].
Kadri, Roubila Lilia ;
Boctor, Fayez F. .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2018, 265 (02) :454-462
[16]  
Kolisch R, 1996, EUR J OPER RES, V90, P320, DOI [10.1016/0377-2217(95)00357-6, 10.1016/S0377-2217(96)00170-1]
[17]   A new shortest path algorithm to solve the resource-constrained project scheduling problem with routing from a flow solution [J].
Lacomme, Philippe ;
Moukrim, Aziz ;
Quilliot, Alain ;
Vinot, Marina .
ENGINEERING APPLICATIONS OF ARTIFICIAL INTELLIGENCE, 2017, 66 :75-86
[18]   Research on Machining Workshop Batch Scheduling Incorporating the Completion Time and Non-Processing Energy Consumption Considering Product Structure [J].
Li, Nailiang ;
Feng, Caihong .
ENERGIES, 2021, 14 (19)
[19]   Joint optimization of preventive maintenance and production scheduling for parallel machines system [J].
Liao, Wenzhu ;
Chen, Maocai ;
Yang, Xiaoxia .
JOURNAL OF INTELLIGENT & FUZZY SYSTEMS, 2017, 32 (01) :913-923
[20]   Energy management in production: A novel method to develop key performance indicators for improving energy efficiency [J].
May, Goekan ;
Barletta, Ilaria ;
Stahl, Bojan ;
Taisch, Marco .
APPLIED ENERGY, 2015, 149 :46-61