Multi-agent based reliability enhancement scheme for IEC61850 substation

被引:0
作者
Rim, Seong-Jeong [1 ]
Lim, Seong-Il [2 ]
Lee, Seung-Jae [1 ]
机构
[1] Myongji Univ, Next Generat Power Technol Ctr, San 38-2, Yongin 449728, Gyeonggi Do, South Korea
[2] kyungnam Univ, Dept Elect Engn, Masan 631701, South Korea
来源
2008 IEEE/PES TRANSMISSION & DISTRIBUTION CONFERENCE & EXPOSITION, VOLS 1-3 | 2008年
关键词
IEC61850; multi-agents; reliability; SA (substation automation); IED (intelligent electronic device);
D O I
暂无
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
This paper presents the multi-agent based reliability enhancement scheme for IEC61850-based substation automation(SA) system. The proposed scheme improves the reliability of the IEDs in IEEC61850-based SA system using multiagents. Multi-agents detect the fault of IED installed in substation and apply to improvement of reliability in protection and control system of substation. These agents in the SA system embedded in the station unit, the engineering unit, the trouble manager, backup IED and protection and control IED as the thread form. Through the implementation and the case studies of the proposed scheme, the availability is proven.
引用
收藏
页码:1515 / +
页数:3
相关论文
共 4 条
[1]  
[Anonymous], 2002, 61850 IEC
[2]  
Bertsch J, 2003, QUALITY AND SECURITY OF ELECTRIC POWER DELIVERY SYSTEMS, P5
[3]  
DING MS, 2004, 8 IEE INT C DEV POW, V1, P268
[4]  
YU XZ, 2000, INT C POW SYST TECHN, V2, P1029