Production scheduling problem with delivery considerations in a mono-product supply chain environment to minimise the total joint cost

被引:9
作者
Grunder, Olivier [1 ]
Wang, Deyun [1 ]
El Moudni, Abdellah [1 ]
机构
[1] UTBM, Lab Syst & Transports SeT, F-90010 Belfort, France
关键词
production scheduling; mono-product supply chain; genetic algorithm; dominance relation; industrial engineering; COMMON DUE-DATE; EARLINESS-TARDINESS; GENETIC ALGORITHM; IDENTICAL JOBS; MACHINE; COMPLEXITY; PENALTIES;
D O I
10.1504/EJIE.2013.057384
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper chooses a supply chain which involves multiple supply links as the studied object. In each supply link, we consider an integrated scheduling problem in which a set of identical jobs are first processed on a single machine, and then batch delivered to a customer by a transporter. Each job has a due date specified by the customer in each supply link. It is supposed that a job which is finished before its departure date or delivered to the customer before its due date will incur a corresponding inventory cost. The objective is to find a joint schedule for each supply link such that the total cost of the supply chain is minimised. We show that this problem is NP-hard in the maximum capacity of the transporters, and then propose a dominance-related greedy algorithm and a genetic algorithm. Computational results illustrate the efficiency of the proposed heuristics.
引用
收藏
页码:615 / 634