Research on Distortion Field of Inspection Robot around 500kV Substation Transformer

被引:1
|
作者
Li, Yongming [1 ]
He, Shengyu [1 ]
Wang, Xuxu [2 ]
Wang, Xiaowan [1 ]
Guo, Changyong [1 ]
Zou, Anxin [3 ]
Xu, Luwen [3 ]
机构
[1] Chongqing Univ, State Key Lab Power Transmiss Equipment & Syst Se, Chongqing, Peoples R China
[2] Zhejiang Elect Power Co Ltd, Shaoxing Power Supply Co, Shaoxing, Zhejiang, Peoples R China
[3] Chongqing Elect Power Test & Res Inst, Chongqing, Peoples R China
关键词
Inspection robot; electromagnetic field; Substation; Finite Element Method; Charge Simulation Method; Transformer;
D O I
10.1109/CIEEC47146.2019.CIEEC-2019432
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
Artificial intelligence technology has developed rapidly, and inspection robots have been increasingly applied to the inspection work of substations. The electromagnetic environment of the substation is complex, and whether the inspection robot can work normally in a complex electromagnetic environment is a problem worthy of attention. Therefore, this paper establishes an inspection robot model to explore the electric field distribution of the inspection robot during substation operation. The Charge Simulation Method is suitable for the calculation of open domain, and the Finite Element Method is suitable fir the calculation of complex boundary problems. Combining the advantages of the two, this paper uses the mixed calculation of Finite Element Method and Charge Simulation method to analyze the electric field distribution around the inspection robot when it's working. The results of computation show that the electric field around each device is distorted, and the electric field distortion around the top device is the most serious.
引用
收藏
页码:1174 / 1179
页数:6
相关论文
共 50 条
  • [21] Research on transformer on-line monitoring system of 500 kV transformer substation based on vibration method
    Wen-Xing, W. (lf6660506@sohu.com), 2013, International Frequency Sensor Association, 46 Thorny Vineway, Toronto, ON M2J 4J2, Canada (161):
  • [22] Computational Analysis of 500kV Transmission Line Distortion Field near Trees
    Song, Fugen
    Lin, Han
    Lan, Sheng
    INTERNATIONAL JOURNAL OF GRID AND DISTRIBUTED COMPUTING, 2016, 9 (10): : 263 - 272
  • [23] Analysis of 3D electrostatic field in 500kv power transformer
    Wang, YH
    Bai, XM
    Liu, FG
    Yan, WL
    Zhang, GQ
    Wang, JM
    PROCEEDINGS OF THE FOURTH INTERNATIONAL CONFERENCE ON ELECTROMAGNETIC FIELD PROBLEMS AND APPLICATIONS, 2000, : 440 - 443
  • [24] Analysis and research on abnormal causes of lightning impulse test of 500kV transformer
    Qu Limin
    Wang Chao
    Zhang Jian
    Gong Mingchen
    Xu Minhu
    Liang Jianquan
    2022 IEEE INTERNATIONAL CONFERENCE ON ELECTRICAL ENGINEERING, BIG DATA AND ALGORITHMS (EEBDA), 2022, : 245 - 248
  • [25] The Research of 500kV Capacitor Voltage Transformer Ferro-Resonance Problem
    Li, Jun
    Zhang, Shuang
    Zhou, Xian-Bao
    INTERNATIONAL CONFERENCE ON CONTROL ENGINEERING AND AUTOMATION (ICCEA 2014), 2014, : 886 - 892
  • [26] Discussion on Applications of Network Time Synchronization in 500kV Substation
    Zhao Hai-sheng
    Yang Fan
    Zhou Jian
    12TH ANNUAL MEETING OF CHINA ASSOCIATION FOR SCIENCE AND TECHNOLOGY ON INFORMATION AND COMMUNICATION TECHNOLOGY AND SMART GRID, 2010, : 517 - 524
  • [27] An application of expert system to equipment operation of 500kv substation
    Deng, YH
    Zhang, BM
    Yang, YH
    PROCEEDINGS OF THE 3RD WORLD CONGRESS ON INTELLIGENT CONTROL AND AUTOMATION, VOLS 1-5, 2000, : 220 - 224
  • [28] The Anomaly Power Transmission and Analysis at a 500kV GIS Substation
    Qi Geqing
    Wu Gang
    Qi Zhuang
    Meng Fanlong
    Jin Daxin
    Zhang Wei
    Zhang Nan
    Wang Lulu
    4TH INTERNATIONAL CONFERENCE ON MECHANICS AND MECHATRONICS RESEARCH (ICMMR 2017), 2017, 224
  • [29] Optimization Design on 500kV Substation Overhead Concrete Platform
    Qi, Xiao
    Wei, Xiaoguang
    Li, Yanan
    MATERIALS ENGINEERING AND TECHNOLOGY, 2014, 849 : 422 - 426
  • [30] Upgrade of Fujian grid on-Line Stability Control System for the Transformer Operating of 500kV Ningde Substation
    Wang Yunmao
    Su Yi
    Huang Jianhong
    2009 ASIA-PACIFIC POWER AND ENERGY ENGINEERING CONFERENCE (APPEEC), VOLS 1-7, 2009, : 1387 - +