Resource-constrained project scheduling by simulated annealing

被引:135
作者
Boctor, FF
机构
[1] Centre de Service, d’Orientation et de Recherche sur la Compétitivité Internationale et I’Ingénierie de I’Entreprise-Réseau, Université Laval, QC
关键词
D O I
10.1080/00207549608905028
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper presents a new adaptation of the simulated annealing algorithm for solving non-preemptive resource-constrained project scheduling problems in which resources are limited but renewable from period to period. This algorithm is able to handle single-mode and multi-mode problems and to optimize different objective functions. Statistical experiments show the efficiency of the proposed algorithm even in comparison to some Tabu search heuristics.
引用
收藏
页码:2335 / 2351
页数:17
相关论文
共 55 条
[1]  
ALVAREZVALDES R, 1989, ADV PROJECT SCHEDULI, pCH5
[2]  
[Anonymous], 1967, THESIS MIT
[3]  
BELL CE, 1990, NAV RES LOG, V37, P61, DOI 10.1002/1520-6750(199002)37:1<61::AID-NAV3220370104>3.0.CO
[4]  
2-S
[5]  
BOCTOR F, 1994, P EURO WG PMS 4 INT, P63
[6]   SOME EFFICIENT MULTI-HEURISTIC PROCEDURES FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING [J].
BOCTOR, FF .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1990, 49 (01) :3-13
[7]   HEURISTICS FOR SCHEDULING PROJECTS WITH RESOURCE RESTRICTIONS AND SEVERAL RESOURCE-DURATION MODES [J].
BOCTOR, FF .
INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1993, 31 (11) :2547-2558
[8]  
BRAND JD, 1964, 5 U ILL DEP CIV ENG
[9]   PROJECT SCHEDULING WITH RESOURCE CONSTRAINTS - A BRANCH AND BOUND APPROACH [J].
CHRISTOFIDES, N ;
ALVAREZVALDES, R ;
TAMARIT, JM .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1987, 29 (03) :262-273
[10]  
Conover W. J., 1980, Practical nonparametric statistics, V2nd