Major Factors Causing Delay in the Delivery of Manufacturing and Building Projects in Saudi Arabia

被引:28
|
作者
Abdellatif, Hussein [1 ]
Alshibani, Adel [2 ]
机构
[1] KFUPM, Elect Engn Dept, Dhahran 31261, Saudi Arabia
[2] KFUPM, Construct Engn & Management, Dhahran 31261, Saudi Arabia
关键词
industrial projects; delay factors; scheduling; RII; building projects; RESOURCE-BASED THEORY; CONSTRUCTION PROJECTS; COST; ORGANIZATION; ECONOMICS; OVERRUNS; INDUSTRY; RANKING; MODEL; RISK;
D O I
10.3390/buildings9040093
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
There have been many studies done on the causes of delay on construction projects and building projects all around the world. They use different methods, on different geographical areas, and they come up with different results. There are, however, few studies on industrial and building projects. This paper focuses on industrial/manufacturing projects in Saudi Arabia. The aim of this paper is to identify the major causes of delay in the manufacturing projects in Saudi Arabia. The top causes of delay have been identified through a literature survey and interviews with experts from the industrial field in Saudi Arabia. Twenty-two factors have been identified and listed in a survey that was distributed to professionals in the same field. Two categorizations were made: the first is based on the impact of the cause, and the second is based on the frequency of occurrence of the identified cause. It has been found that the top five impacted causes of delay in the delivery of industrial projects in Saudi Arabia are: difficulties in financing project by contractor/manufacturer, late procurement of materials, late delivery of materials, delay in progress payments, and delay in approving design documents, respectively. In terms of frequency, the top five identified causes are: delay in progress payments, difficulties in financing project by contractor/manufacturer, slowness in decision making, late procurement of materials, and delay in approving design documents, respectively. The diversity of the participants is an important point; therefore, the respondents were from different job positions (management, engineering, etc.), and different categories (contractor, owner, manufacturer, consultant, etc.). It is worth noting that this paper serves not only as an authentic study of the causes of delay in the delivery of industrial projects in Saudi Arabia which is a field that is not widely covered, but also as a fresh paper that gives an indication of the changes that happen to the business over time as compared to previous work.
引用
收藏
页数:15
相关论文
共 50 条
  • [21] Analysis of Project Failure Factors for Infrastructure Projects in Saudi Arabia: A Multivariate Approach
    Ikediashi, Dubem I.
    Ogunlana, Stephen O.
    Alotaibi, Abdulaziz
    JOURNAL OF CONSTRUCTION IN DEVELOPING COUNTRIES, 2014, 19 (01) : 35 - 52
  • [22] Factors influencing change orders in oil and gas construction projects in Saudi Arabia
    Alkhalifah, Sadeq J.
    Tuffaha, Firas M.
    Al Hadidi, Laith A.
    Ghaithan, Ahmad
    BUILT ENVIRONMENT PROJECT AND ASSET MANAGEMENT, 2023, 13 (03) : 430 - 452
  • [23] Impact of Endogenous Risk Factors on Risk Cost in PPP Projects in Saudi Arabia
    Alfraidi, Yahya
    Alzahrani, Saleh Mohammed
    Abdelhafez, Mohamed Hssan Hassan
    Boussabaine, Halim
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2020, 10 (04) : 6087 - 6091
  • [24] Comparative Analysis of Factors Causing Delay in Residential Construction Projects in Pakistan
    Din, Zia Ud
    Raza, Ali
    Khan, Muhammad Babar
    CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 640 - 648
  • [25] An Investigation into the Causes of Payment Delays and Deliberate Delay Tactics in Public Construction Projects in Saudi Arabia
    Bageis, Abdulrahman Salem
    BUILDINGS, 2024, 14 (06)
  • [26] Influence of BIM and Lean on mitigating delay factors in building projects
    Perez, Yeimi
    Avila, Jeffer
    Sanchez, Omar
    RESULTS IN ENGINEERING, 2024, 22
  • [27] Standardising the route to project handover to improve the delivery of major building projects
    Too, Judy
    Ejohwomu, Obuks A.
    Bukoye, Teslim Oyegoke
    Hui, Felix Kin Peng
    Oshodi, Olalekan Shamsideen
    INTERNATIONAL JOURNAL OF BUSINESS PERFORMANCE MANAGEMENT, 2023, 24 (02) : 175 - 199
  • [28] Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects
    Sanchez, Omar
    Castaneda, Karen
    Mejia, Guillermo
    Pellicer, Eugenio
    CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 223 - 231
  • [29] Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China
    Ji, Yingbo
    Qi, Lin
    Liu, Yan
    Liu, Xinnan
    Li, Hong Xian
    Li, Yan
    APPLIED SCIENCES-BASEL, 2018, 8 (11):
  • [30] Categorization of Saudi Arabia's construction delay factors using factor analysis technique
    Rahman, I. A.
    Al-Emad, N.
    Nagapan, S.
    ENGINEERING CHALLENGES FOR SUSTAINABLE FUTURE, 2016, : 177 - 181