Construction project productivity evaluation framework with expanded system boundaries

被引:8
作者
Zhan, Wenting [1 ]
Pan, Wei [1 ]
Chen, Le [1 ]
机构
[1] Univ Hong Kong, Dept Civil Engn, Pok Fu Lam, Hong Kong, Peoples R China
关键词
Productivity; Construction project productivity; Productivity evaluation; System boundaries; Systemic value; Hong Kong; LABOR PRODUCTIVITY; PERFORMANCE; MODEL;
D O I
10.1108/ECAM-12-2019-0691
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose While the investment in construction projects has increased over the past few decades, low construction project productivity (CPP) appeared to be persistent, thereby reflecting an "investment-in-failure" paradox between the investment and CPP. Hence, this paper aims to develop a systematic and holistic CPP evaluation framework to explain the apparent paradox in the construction industry. Design/methodology/approach The paper first reviews the literature about the theories of system, production, principal-agent and project success evaluation to re-conceptualise the CPP and proposes a two-stage CPP evaluation framework. The framework is subsequently explored through a sequential qualitative mixed-methods design within the context of the Hong Kong construction industry by combining 32 semi-structured interviews with senior industry experts and exploratory case studies, with three real-life construction projects. Findings The paper identifies three system boundaries for CPP evaluation, that is, parameter, timeframe and stakeholder, and develops a two-stage CPP evaluation framework to indicate site efficiency and utilisation effectiveness, thereby accessing the productivity of both the construction and post-construction stages. The "investment-in-failure" paradox associated with current CPP evaluation approaches is primarily attributed to the narrowly defined CPP boundaries. Research limitations/implications The qualitative exploration of the evaluation framework only focusses on the Hong Kong construction industry. Further case studies within other urban contexts could be used to improve the generalisability of the findings. Quantitative research is also necessary to advance theoretical development of the two-stage CPP evaluation. Practical implications The systemic CPP conceptualisation and the two-stage CPP evaluation framework support the systems thinking of industry stakeholders and enable them to formulate holistic strategies for long-term CPP enhancement. Originality/value The research demonstrates the needs to expand the system boundaries of CPP to reflect its systemic value and to shift the paradigm of CPP evaluation from being output-orientated and quantity-focussed to being outcome-orientated and value-focussed.
引用
收藏
页码:863 / 885
页数:23
相关论文
共 60 条
[1]   Trends of productivity growth in the construction industry across Europe, US and Japan [J].
Abdel-Wahab, Mohamed ;
Vogl, Bernard .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2011, 29 (06) :635-644
[2]   Dynamics of Project-Driven Production Systems in Construction: Productivity Function [J].
Antunes, Ricardo ;
Gonzalez, Vicente A. ;
Walsh, Kenneth ;
Rojas, Omar .
JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2017, 31 (05)
[3]   A Production Model for Construction: A Theoretical Framework [J].
Antunes, Ricardo ;
Gonzalez, Vicente .
BUILDINGS, 2015, 5 (01) :209-228
[4]  
Bertalanffy L.v., 1968, General System Theory: Foundations, Development, Applications, DOI DOI 10.17059/2011-4-28
[5]   The Open Secret of Values: The Roles of Values and Axiology in Project Research [J].
Biedenbach, Thomas ;
Jacobsson, Mattias .
PROJECT MANAGEMENT JOURNAL, 2016, 47 (03) :139-155
[6]  
Blaikie N., 2009, DESIGNING SOCIAL RES
[7]   Quality Change and Implications for Productivity Development: Housing Construction in Sweden 1990-2010 [J].
Borg, Lena ;
Song, Han-Suck .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2015, 141 (01)
[8]   System model for analyzing design productivity [J].
Chang, AS ;
Ibbs, W .
JOURNAL OF MANAGEMENT IN ENGINEERING, 2006, 22 (01) :27-34
[9]  
Cooke-Davies T, 2002, INT J PROJ MANAG, V20, P185, DOI 10.1016/S0263-7863(01)00067-9
[10]  
Dewett K.K., 2009, MODERN EC THEORY